Use Time Constraints
Use the Links & Constraints tab to apply constraints that control the start or finish date of the activity.
Ways to access
Select an activity in a time-distance view and select a constraint in the Object Properties pane > Links & Constraints tab.
Options
Possible constraints include:
Start on - This constraint sets the start date to the given date in the Start field.
Start on or before - The activity cannot start later than the given date in the Start field.
Start on or after - The activity cannot start earlier than the given date in the Start field.
Finish on - This constraint sets the finish date to the given date in the End field.
Finish on or before - The activity cannot finish later than the given date in the End field.
Finish on or after - The activity cannot finish earlier than the given date in the End field.
Work Between - The activity cannot start earlier than the given date in the Start field and cannot end after the given date in the End field.
Deadline - This is similar to the Finish constraint on or before, but allows the activity to slip beyond the given End date when rescheduled.