Delete Calculations from a Schedule
To delete all calculation information from an existing construction schedule without changing the construction schedule so that the TILOS file contains only information about the start time, end time, start route, and end route for each process, follow these general steps:
Mark 400 processes in the process list (only works up to a maximum of 400 processes at once).
On the Calculation tab switch to Power under Calculate.
Remove the quantity information on the Calculation tab or change the calculation of the length using the Work Quantity Factor.
Repeat for all operations
If there were processes that are calculated using profiles, check them again (duration).
If operations are calculated using resources, also remove this calculation.
Now there should be no more calculation values in the file and the processes are otherwise retained.