Construction Costing Breakdown.
The elemental cost breakdown for months was calculated in tandem with the schedule produced by G7's Consultancy team. Sub categories from the cost plan were broken down in order to cost each elemental cost per month during the construction process. For example, section 3. Finishes was broken down and valued for each section, the the cost per day was valued for 3A, 3B and 3C - assigning each section a number of days and the cost per day within each month.
Created by Connor Littlemore