A.   Reviews of Technical Divisions’ and Research Centers’ WFP for the purpose of fund allocation and identification of priorities that ERDB NEP shall program for the current year

Office/Division 

Planning and Information and Communications Technology Division (PICTD)

Classification 

Complex 

Type of Transaction 

Government to Government (G2G) 

Who May Avail 

Technical Divisions and Research Centers 

CHECKLIST OF REQUIREMENTS


WHERE TO SECURE


1.    Memo from the Division/RDEC Head re: submission of WFPs of each Division/Center

Division Chiefs/RDEC Heads, ERDB 

2.    Submitted WFPs with attachments (Travel Plan, OGS, PPMP-Supplies) 

Division Chiefs/RDEC Heads, ERDB 

3. Comments on the corrections found in the submitted WFP to be forwarded to the Divisions/Research Centers (RCs)  for their revisions

PICTD-PPS 

CLIENT STEPS

AGENCY ACTION 

FEES TO BE PAID

PROCESSING TIME

PERSON RESPONSIBLE

1.    Divisions and RDECs submit the 1st draft of WFP for newly approved RDE projects to PICTD thru email.

Forwards the submitted 1st draft of WFP to PICTD-PPS for review 

None 

30 minutes 

PICTD-OC

Reviews the submitted 1st draft of WFP of newly approved RDE projects for the purpose of fund allocation and identification of priorities that ERDB NEP shall program.

3 working days 

PICTD-PPS Staff

Coordinates and returns the WFP with corrections and comments to the Divisions/RDECs for their revision. 

30 minutes 

PICTD-PPS staff 

2. Divisions and RDECs submits the revised WFPs (2nd draft) of newly approved RDE project to PICTD for further review. 

Further review and evaluate the revised WFP to determine if the comments and recommendations of the concerned focal person has been observed and adopted.

PICTD-PPS to return to the concerned Divisions and RDECs the WFP subject of their evaluation for the concurrence and initials/signature of the concerned officials 

1 and ½ working days 

PICTD-PPS Staff

3. Divisions and RDECs to finalize their respective WFP and will forward the same to PICTD-PPS with initials and signature of concerned personnel and officials, thru e-mail. 

If found in order, PICTD-PPS finalizes the WFP of the Divisions and RDECs.

 

Concerned focal person of PICTD-PPS will forward the final WFP to the Chief PICTD for final review and signature.

4 hours 

PICTD-PPS Staff

The PICTD Chief does final review, affixes initial and endorses the WFP for approval. 

3 hours 

PICTD Chief

Forwards the WFP to OAD for AD’s signature (recommending approval) 

2 hours 

PICTD-OC staff, OAD Document Receiver, AD 

OAD staff forwards the WFP signed by AD for the Director’s approval. 

1 working day 

OAD staff and Director 

OD staff forwards the approved WFP to PICTD for appropriate action. 

10 minutes 

OD Staff 

PICTD staff forwards the approved WFPs to Records Unit for dissemination to respective Divisions and RDECs. 

10 minutes 

PICTD Staff 

Records Unit disseminates the approved WFPs to the Divisions and RDECs. 

10 minutes 

Assigned personnel in the Records Unit 

EXPECTED TURN AROUND TIME 

6 working days, 6 hours and 30 minutes 

B.   Reviews of Technical Divisions’ and Research Centers’ WFP for the purpose of fund allocation and identification of priorities that ERDB NEP shall program for the next fiscal year

Office/Division 

Planning and Information and Communications Technology Division (PICTD) 

Classification 

Complex 

Type of Transaction 

Government to Government (G2G) 

Who May Avail 

Technical Divisions and Research Centers

CHECKLIST OF REQUIREMENTS

WHERE TO SECURE

1.  Memo from the Division/RDEC Head re: submission a full set of WFPs for the next fiscal year of each Division/Center 

Division Chiefs/RDEC Heads, ERDB 

2. Submitted WFPs with attachments (Travel Plan, OGS, PPMP-Supplies)  

Division Chiefs/RDEC Heads, ERDB 

3. Comments on the corrections found in the submitted WFP to be forwarded to the Divisions/Research Centers (RCs)  for their revisions 

PICTD-PPS 

CLIENT STEPS

AGENCY ACTION 

FEES TO BE PAID

PROCESSING TIME

PERSON RESPONSIBLE

1.    Divisions and RDECs submit the 1st draft of RDECs and Divisions WFPs for the next fiscal year to PICTD thru email.

Forwards the submitted 1st draft of WFP to PICTD-PPS for review 

None 

30 minutes 

PICTD-OC

Reviews the submitted 1st draft of RDECs and Divisions WFPs for the next fiscal year for the purpose of fund allocation and identification of priorities that ERDB NEP shall program. 

None 

3 working days 

PICTD-PPS Staff and

AFMD-Budget Section

Coordinates and returns the WFP with comments and suggestions including corrections to the Divisions/RDECs for their revision. 

30 minutes 

PICTD-PPS staff 

2. Divisions and RDECs submits the revised WFPs (2nd draft) for the next fiscal year to PICTD for further review.

Further review and evaluate the revised WFP to determine if the comments and recommendations of the concerned focal person has been observed and adopted.

PICTD-PPS to return to the concerned Divisions and RDECs the WFP subject of their evaluation for the concurrence and initials/signature of the concerned officials 

1 and ½ working days 

PICTD-PPS Staff and

AFMD-Budget Section

3. Divisions and RDECs to finalize their respective WFP and will forward the same to PICTD-PPS with initials and signature of concerned personnel and officials, thru e-mail. 

If found in order, PICTD-PPS finalizes the WFP of the Divisions and RDECs.

 

Concerned focal person of PICTD-PPS will forward the final WFP to the Chief PICTD for final review and signature.

4 hours 

PICTD-PPS Staff

The PICTD Chief does final review, affixes initial and endorses the WFP for approval. 

3 hours 

PICTD Chief 

Forwards the WFP to OAD for AD’s signature (recommending approval) 

2 hours 

PICTD-OC staff, OAD Document Receiver, AD 

OAD staff forwards the WFP signed by AD for the Director’s approval. 

1 working day 

OAD staff and Director 

OD staff forwards the approved WFP to PICTD for appropriate action. 

10 minutes 

OD Staff 

PICTD staff forwards the approved WFPs to Records Unit for dissemination to respective Divisions and RDECs. 

10 minutes 

PICTD Staff 

Records Unit disseminates the approved WFPs to the Divisions and RDECs. 

10 minutes 

Assigned personnel in the Records Unit 

EXPECTED TURN AROUND TIME 

6 working days, 6 hours and 30 minutes