St. Peter Claver School is hoping to complete two projects in their male and female bathrooms. The floor in the male bathroom needs to be tiled for hygiene purpose and better cleaning.
Additionally, in both the male and female bathrooms, termites and water damage have left the vanities disintegrating. Replacing them with cement will alleviate both of these issues.
225 tiles 12x12 $641.91
20 bags tinset $490.00
4 bags grout $188.00
1 pk spacers $4.50
Contingency fee $100.00
Total: $1424.41
144 4 inch blocks $280.80
10 bags cement $230.00
6 lengths 3/8 inch steel rod $120.00
2 # tying wire $6.00
2# two and a half inch nails $8.00
4 pieces 1x12x12 $108.00
Contingency fee $100.00
Total: $852.80