This application deals with the control of three PVC Mixing Plants,
but configured differently to Applications 5 & 9
The project involved panel design, plc and HMI application software, and on site commissioning.
Key components:- Mitsubishi Q series PLCs, MelsecNet/H, Beijers E1000 series operator interfaces, Mitsubishi Inverters
PJC Systens were approached when the customer was looking to build a mixing house, on site, rather than transporting material from their sister company many miles away. The plan was to move three mixing plants to the site and to integrate them into a total mixing solution for the business.
One of the mixers was being moved complete with it's control system controlling the feed to, and discharge from it. It soon became apparent, however, that this would not suit the proposed configuration.
PJC Systems secured the contract to control everything from:
delivery of raw materials to the bank of silos
transfer of materials from the silos to all three mixing plants
control of mixer HSB7
transfer of blended material from all three mixers to internal day bins
transfer from day bins to compounders, and back to compounded day bins
transfer from day bins to silos
When the second mixer was moved to the site, there were a number of modifications necessary which PJC Systems carried out. The third mixer has not yet been moved.
The central part of the system is a number of Mitsubishi Q series plcs, communicating with each other over MelsecNet H. Each mixer's PLC then communicates via ethernet with it's own Beijers E1151 Operator Interface.
Some of the control panels existed before PJC Systems' involvement but the manufacture of the other panels was by a local panel manufacturer with whom we work very closely.
The slideshow above shows some of the plant that PJC Systems controlled. The plant comprises 2 x PVC Mixing Plants, producing foam, rigid and skin material. PVC, and additives are accurately weighed, loaded into the high-speed mixer, and mixed vigorously until the batch reaches the required discharge temperature (approx 120 deg C), when it is discharged into the cooler. It is then cooled to a temperature at which it will convey easily (approx 40 deg C) when the material is sieved, before being conveyed to storage silos.
(PJC Systems do not carry out any work beyond the SCADA system we install. All access to the factory network is to be carried out by the customer)