All equipment must be connected to simulate a live on site environment; to begin:
Ensure all switches power cables are plugged in.
A. Add any necessary Jumpers.
Power on the router and ensure connection to the switch through LAN on the first switch and the internet source through WAN.
Power on the EZOutlet and ensure LAN connection to the first switch.
Power on the NAS and ensure LAN connection on NIC 1 to the first switch.
A. Ensure the power source for the NAS is ONLY through the EZOutlet.
If P2Ps are pressent, begin setting up the site according to the design, placing remote endpoints as designated. Ensure no loopbacks are present and all Client Bridges are isolated.
Begin plugging in remaining devices.
A. ie. Cameras, Speakers, Strobes.
Verify connectivity of all devices and VPN tunnel.
Fill out the IP according to placement of devices and mark down switch and port numbers.
Fill out Zuper for Site Enablemement and ensure the install record is filled accordingly.
Trouble shoot as needed until Site Enablement is completed.