COST PLAN ANALYSIS
Before an Elemental Cost Plan can be generated, the proposed Client Requirements must be reviewed.
The Client (BHD) is considering undertaking a property development in Berlin and has identified two sites of potential interest.
BHD have provided the following key considerations:
· BHD are keen to explore the potential to add more floor space to the property.
· BHD are an experienced mixed-use developer.
· BHD are keen to see something that is sustainable, meets local objectives and stands out as an exemplar project.
After an initial assessment and a preliminary meeting with the client on the evening of 2nd June, Building 1 has been chosen as the preferred site based on the following assumptions:
· The Client is assumed to want to maximise the financial return on their investment.
· The Client is assumed to have a reasonable budget to develop the two identified sites.
· The Client is assumed to hold the following values in order of precedence:
o 1. Cost
o 2. Time
o 3. Quality
The existing building will be refurbished against the criteria listed within the Preliminary Assessment.
Refer to ‘Table 1: Building 1, Corner of Mollstrasse and Otto-Braun Strasse – Existing Building Refurbishment Observations:’ for an assessment of the refurbishment criteria against the Elemental Cost Plan criteria
The approximate Gross Internal Floor Measure is calculated as 26.49m x 79.42m = 2,103.84m2.
A full comparative elemental cost plan is generated by downloading a similar elemental cost analyses from BCIS. Refer to Fig 1 Reference - BCIS - Warehouse - #33351 (Lewisham, London) Reference Project - Cost Plan’ for the Reference Cost Plan.
The BCIS search was narrowed to the following criteria:
1. Basic Parameters:
800. Residential Facilities – 818. Housing with shops, offices workshops or the like
2. Building Specification:
Floor Area – Gross Internal Floor Area Custom Range – 1000 to 4000 m2
Number of Storeys – Number of Storeys Range 6 to 14nr
The reference file was adjusted to the following criteria:
Re-based Location to London
Re-based Date to Q1 – 2026
Rebased to Berlin using the ‘International Construction Cost Index 2024’. Arcadis (2022).
01 - London Average Location Index – 223
25 - Berlin Average Location Index – 153
Rebase value for Cost Plan = 153/223 = 0.686
BCIS. (5.C.E)
Adjustments are made to the Reference Cost Plan to make consideration for differences in the level and type of refurbishment:
BCIS. (5.C.E)
The following adjustments to the Reference Cost Plan should be made to allow for differences in the level and type of refurbishment between the Reference Cost plan and the Building 1 Proposal.
MOOR CONSTRUCTS
Moor Construction is a Building and Civil Engineering Construction Company based in Sheffield, United Kingdom that specializes in Building, Civil Engineering and project management.
CONTACT INFO
City CamCity Campus, Howard Street, Sheffield, S1 1WB, UK
Phone +44 (0)114 225 5555
OUR SERVICES
Building Construction
Civil Engineering Works
Property Development / Real Estate
Specialized Construction Services
Development Consultancy
Project Management Services