(a) General
The CD-PUD zone district review procedure is an expedited approval procedure that applies only within the CD-PUD zone district to applications for development pursuant to the residential or commercial agricultural development options.
(b) Pre-Application Meeting
A pre-application meeting pursuant to Sec. 2-20-30 is required prior to submission of an application.
(c) Procedures
Applications for approval of a CD-PUD Development Plan shall comply with the provisions of Section 2-30-40 and 2-40-10 for a rezoning to CD-PUD. Applications for approval of a CD-PUD Development Plan shall also comply with the provisions of Sec. 2-40-50 applicable to other PUDs except that approval shall only require a single review of the application by the Planning and Zoning Commission, and a single decision on the application by the Board, as shown in Table 2-1.
(d) Requirement for GMQS Allocation or TDRs in CD-PUD Zone District
If the applicant applies for development under the CD-PUD residential or commercial agricultural development options described in Sec. 3-70-40(h) or (i), the development shall be eligible for a GMQS exemption pursuant to Sec. 6-30-90. TDRs may only be used as specified in Sec. 3-70-40(h) or (i).
(e) Criteria for Approval
A CD-PUD Development Plan may be recommended for approval by the Planning and Zoning Commission, and may be approved by the Board only if those bodies find that all of the following criteria have been met:
(f) Vested Right
A CD-PUD Development Plan is a Site Specific Development Plan, as defined in Sec. 2-20-170(b), and shall result in the establishment of a vested right.