Based upon review of the pre-application submittals and the information obtained at the pre-application meeting, the Director may determine that a Finding of No Significant Impact (FONSI) is warranted or that a Permit is required. Such determination may be made by the Director at such time as sufficient information is provided by the applicant after the pre-application meeting.
If pursuant to Section 12.30.30 a Permit is required, then the following permit application procedure shall apply:
The Director may waive one or more of the submittal requirements when the submittal information would not be relevant to whether the Project complies with the approval criteria. Additional materials may be required under Sections 12.30.70 for a particular type of Project.
1. Information describing the applicant.
2. Information describing the Project.
3. Property rights, other permits and approvals.
4. Description of the technical and financial feasibility of the Project.
5.Socioeconomic impacts
6. Environmental impacts.
7. Hazardous materials description.
8. Monitoring and Mitigation Plans.
9. Additional Information may be necessary. The applicant must supply any other additional information and documentation necessary for the Permit Authority to make a determination regarding whether the Project meets the applicable Approval Criteria in Section 12.40. In addition, the Director may request that the applicant supply additional information related to the Project if the Permit Authority will not be able to make a determination on one of the Permit Application Approval Criteria in Section 12.40 without the additional information.
10. For each alternative site or expansion area for which a permit is being sought by the applicant, if any, the information specified in subsections (1) through (9) of this Section. An application need not meet the identified submission requirements for other than the particular development alternative for which a permit is being sought in order for the application to be considered complete, but the description of alternative sites and expansion areas must be sufficiently detailed so as to adequately inform the Permit Authority.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing to develop land use in Mineral Resource Areas.
A. Flood Hazard Area. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing to develop land use in flood hazard areas.
B. Geologic Hazard Area. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing land use in Geologic Hazard Areas.
C. Wildfire Hazard Area. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing land use in Wildfire Hazard Areas. The required maps shall be prepared and signed by a professional forester.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing to develop land use in Historical, Paleontological and Archeological Resource Areas.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing to develop land use in Significant Wildlife Resource Areas.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing to develop land use in Natural Resource Areas comprised of shorelands.
A. The following submittal requirements apply to applications proposing to develop land use in areas around Airports and Heliports:
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing to develop land use in areas around Major Facilities of a Public Utility.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing to develop land use in areas around Interchanges Involving Arterial Highways.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing to develop land use in areas around Rapid or Mass Transit Facilities.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing Major Facilities of a Public Utility.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing Site Selection and Development of Solid Waste Disposal Sites.
A. The following submittal requirements apply to applications proposing to locate an Airport or Heliport.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing location and construction of arterial highways, interchanges or collector highways.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing stations or terminals associated with a rapid or mass transit system.
A. In addition to the submittal requirements in Section 12.30.60, the following submittal requirements apply to applications proposing fixed guideways.