Any physical or operational change in the construction, operation, purposes, goals, uses, effects, capacity or storage of a Water and Sewer Project from that approved by the Permit Authority shall require a permit amendment, unless otherwise exempt.
A permit amendment will be subject to the following requirements and procedures:
(a) Permit Application Submittal Requirements.
A copy of the current Permit and reasons for amendment.
As-built drawings of the Project, if available.
Drawings and plans of proposed changes to the Project.
Additional or changed mitigation plans.
Statement of need for amendment.
Site Plan.
Vicinity map.
Written report of how amendment satisfies the criteria in Sections 12.40.10, 12.40.20 and 12.40.30.
(b) Permit Amendment Procedure.
The applicant shall meet with the Director to discuss the proposed permit amendment.
Application submittal requirements shall be reviewed by the Director.
Subsequent to the meeting, the Director shall determine whether the modified Project would satisfy the criteria contained in Sections 12.40.10, 12.40.20 and 12.40.30, or whether additional conditions would be necessary to ensure compliance.
If the Director deems that the modified Project would not satisfy applicable criteria without additional conditions, the proposed modification shall require a new Permit.
If the Director deems that the modified Project would satisfy applicable criteria without additional conditions, the Director shall make a Finding of No Significant Impact and a resolution for an amended Permit shall be presented to the Permit Authority for its consideration.