Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Made 4 coil test beds for 24 and 32 gauge wire
Qualitatively tested them against 36 gauge test bed
Need to test efficacy of stirring positions that share coils
Accomplishments from Previous Week
Tested different wire gauges in magnetic coils
Measured coil resistances to later calculate current, power draw and field strength
Manufactured iron cores in house
Added button for speed control to stirrer prototype
Created 3D model for casing
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Build 6 coil array to test interference
Coil winding - Chris
Core turning - Nick
Simulate different coil dimensions - Nick, Jordan and Edward
Manufacture housing - Siddarth
Translate code to Raspberry Pi - Edward and Jordan
Analysis of current designs -
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
In Person 04/18/17
Continue down two product line path
Hard button controlled stirrer
Software UI controlled stirrer
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
In Person 04/17/17
More analysis
Power consumption - determined from coil array resistance and voltage
Field strength - determined from coil array resistance, voltage and number of turns from manufacturing
Stir bar speed - IKA has a machine to measure this
Temperature - can be found from current and voltage and coil dimensions
Put a vial rack on stirrer to prevent them from falling off
Coil manufacturing
Get in touch with manufacturers from IKA
Isaiah Ferguson at Calit2
ACME Mechatronics
Save spend dat money
Official quote received from Soft Magnetic Metal Supplier $882.4 for material to make new cores and flat platesÂ
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Multiple stirring positions could have too much interference
Resources or Information Required but not Available
None
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$193.28 Spent, $4,806.72 Remaining
Progress on Report and Webpage
Webpage currently in same state as before
Report updated, being worked on continuously