https://deldot.gov/projects/index.shtml?dc=details&projectNumber=T200711201
Widen to provide turn lanes at SR 24/Mount Joy Road/Oak Orchard Road and SR 24/Bay Farm Road/Autumn Lane.
This project is identified as a high crash location as part of the Delaware Department of Transportation (DelDOT) Highway Safety Improvement Program (HSIP). Recommendations were made from the SR 24, SR 30 to Love Creek Traffic Study performed in November 2010. The study determined the need for operational improvements to address safety deficiencies and to accommodate future traffic volumes.
Design and Planning
Construction Start Date: Spring 2021
Construction End Date: 2023
Design and right of way acquisition are underway. Some advanced utility relocation work began in Spring 2020. Roadway construction is anticipated to begin in the spring of 2021.