10.03.2016

Add category selection in backend (JVR)

Analysis of tests and recommendations (RME)

Include Dashbot (analytics) middleware in chatbot (SBE)

10.04.2016

Show Deals by category in chatbot (SBE)

Add point of sale in backend (JVR)

Fix for file upload (JVR)

Category and deal list for backend (RME)

Drafting of test concept (RME)

10.05.2016

Hello and help controller (SBE)

Expiration and publication date conditions for Deals (SBE)

Styling of backend (RME)

Drafting of test concept (RME)

Pulled information for dashboard in backend (JVR)

10.06.2016

Static menu for chatbot (SBE)

Add user middleware in chatbot (SBE)

Setup of deployment, including necessary fixes of code (JVR)

Design of icon and product images (JVR)

Wording for chatbot messages (RME)

Drafting of questionnaire (RME)

10.07.2016

Meeting with project manager: presentation of chatbot and backend, presentation of

UX test, initial feedback (SBE, RME, JVR)

Included quick replies in responses (SBE)

Correct product images (SBE)

10.08.2016

Incorporated feedback from project manager (small adjustments) (SBE)

The Chat Bot logo proposal

https://sites.google.com/a/gapps.hswlu.ch/ice2016/home/3-valora/week-4/Valora_the%20chatbot%20logo%20proposal.png

Chatting with the prototype

https://sites.google.com/a/gapps.hswlu.ch/ice2016/home/3-valora/week-4/Valora_Chatting%20with%20the%20prototype.png

Coding is not the only thing we do

https://sites.google.com/a/gapps.hswlu.ch/ice2016/home/3-valora/week-4/Valora_Coding%20is%20not%20the%20only%20thing%20we%20can.png

Deployment in progress on Heroku

https://sites.google.com/a/gapps.hswlu.ch/ice2016/home/3-valora/week-4/Valora_Deployment%20in%20progress%20on%20Heroku.png