Project Management Specialist
One of the spaces I was given to use was the Automotive Collison Repair Building (ABR) which sits directly across the campus street from the east side entrance of the automotive building.
It has one classroom, an open shop in the center, a small tool room, a reception area (shown to the right), instructors office, and a drive thru paint booth and prep area. There are three high bays on the north and two high bays on the south side with one on the east side of the building.
New exhaust system
To prepare the building for the temporary relocation of the automotive program, it would need some things.
For example, since we were going to bring over 6 lifts, we added exhaust systems (shown) and a new electrical panel; the lifts and exhaust reels are so close to the gas heaters (shown), we had them turned off and added new heaters (also shown); added auto-shut offs and Co2 sensors.
New exhaust system
Instructors office
When I was assigned to this project, the building was being used by facilities to store misc items, so before I was able to have the JOC walk thru, I needed the space to be empty. If you would like to learn even more, please click here.