Site Survey Completed Date
Design Started Date
Design Completed Date
Permit Submitted Date
Permit Approved / Received Date
Install Scheduled Date
Install Completed Date
Inspection Scheduled Date
Monitoring Site ID
Monitoring Full Access Granted to Seamless (monitoring@seamlessenergy.com)
System Commissioned & Verified Functional
Stamped / Approved Planset
Permit Package
Utility pre-approval
Final Inspection Passed Date
Permission to Operate Requested Date
Permission to Operate Granted Date
System Activated / Verified Operational
Signed final inspection card or portal screenshot showing "Passed" / "Finaled" / "Completed" status
Permission to Operate Documentation (screenshot or letter from utility confirming approval)
NTP should be granted, and the following fields must be completed:
Install Schedule Date
Install Completed
Additional for roofing projects:
Permit Submitted Date
Permit Approved Date
Tear-Off Schedule Date
Tear-Off Completion Date
Installation photos
Additional for roofing projects:
Approved Permit
Tear off photos
After completing all required fields and uploading the necessary documents, please email operations@seamlesshome.com for review and to submit for funding.
Loan Documents signed by Borrower and Co-Borrower, as applicable.
Project Info
To be entered in SubHub under "GoodLeap Financed Projects"
Verify Loan Details:
To be completed by SolarQuote. Please email projectmanagement@seamlessenergy.com
HIC Upload
To be submitted in SubHub under "GoodLeap Financed Projects"
Welcome Call
Borrower will receive link to complete Welcome Call directly from GoodLeap. this link is sent at the time of Agreement Signing.
Agreement Documents signed by Homeowner
Work Order:
To be completed by Seamless. Please email projectmanagement@seamlessenergy.com
Project Verification Survey
Customer will receive link to complete Welcome Call directly from GoodLeap. this link is sent at the time of Agreement Signing.
Utility Bill
Will be uploaded at time of sale in the proposal in SubHub.
NTP (M0) Requirements Include:
Initial account/system details
Underwriting documents
Signed contract & completed customer task
Install Contract(s): HIC
To be uploaded by Seamless. Please email projectmanagement@seamlessenergy.com
Loan Agreement: Sent by Sunlight to customer for signature
Approved customer qualification
Signed Loan Packet submitted by homeowner via DocuSign
Successfully completed Digital Terms of Agreement (DTA)
Payment Method Collection by homeowner - ACH info via email or calling Support to opt out
System size + cost, including HVAC portion (if applicable, not to exceed 45% of loan total) ***only applicable for Solar+ Loans
Home Improvement Contract (HIC) and all additional improvement invoices uploaded to Concert Portal
For Battery only projects, the warranty (manufacturer or third party warranty) needs to be listed on the HIC to help prevent the need for additional outreach.
Approved customer qualification
Signed and completed Homeowner packet
Prepaid Energy Agreement
Installation Agreement
Loan Note
Disclosure form if in CA
Successfully completed Digital Terms of Agreement (DTA)
Payment Method Collection by homeowner - ACH info via email or calling Support to opt out
Upload latest utility bill
Greentech Branch - to be completed by Seamless. Please email projectmanagement@seamlessenergy.com
Required Docs:
Utility Bill
The first page of the utility bill must be uploaded to the portal.
The bill needs to show:
Account holder name
Address
Name of utility
NEM Agreement Application/Interconnection Application
The doc you upload to the portal needs to be the same completed doc you send to the utility. It doesn’t need to be countersigned by the utility or accepted yet.
Confirmation Call
Upload a note as a pdf saying the call was completed. You can also upload the email that the sale rep receives once the call is completed.
2D Drawings (in pdf form)
These are the CAD drawings or engineering plans for the system that you are using for your permit application. Send the complete plans not just the first page. These plans must be in PDF form.
BOM section should be on the first page of the plans and must list the following information for equipment.
Modules: SKU, QTY, Manufacturer
Inverters: SKU, QTY, Manufacturer
Battery: SKU, QTY, Manufacturer
Racking: SKU, QTY, Manufacturer
Final Design Package -- the package of information submitted to the Authority Having Jurisdiction, including but not limited to, site plan, wiring schematic, equipment specification sheets, and structural design information
a. Customer Address matches EnFin’s records
b. Must be prepared by a qualified PE and provide engineering stamp or engineering letter (structural), and racking design documentation in accordance with AHJ and/or incentive program requirements, as applicable.
c. Layout in Final Design Package must match the layout in final proposal and shade report
Proposal
a. A revised proposal if changes were made post M0 Approval
Shade Report
a. Layout must match the layout in final proposal
b. Must be generated by EnFin approved proposal-generating tool
Additional Market Documents
a. Illinois:
i. IL Shines Disclosure signed prior to TPO Agreement
ii. ComEd: Signed Battery Disclosure for PV+Battery projects
Install Completed Date (will be entered in Subcontractor Hub under "GoodLeap Financed Projects")
Installation Verification Case
Documentation required:
As-Built Plan Set - documentation must include:
Property Address
Site Plan
Single Line Diagram
Bill of materials showing all equipment installed with count of equipment installed.
Photos of EACH Installed Inverter
Photos of EACH Installed Inverter or Combiner Box
For Enphase inverters, provide a clear image of the installed Enphase Combiner
For Tesla PW3, provide a clear image of the installed PW3
Photos of EACH Installed Battery with components (max: 10)
Photo of Installed/Mounted Battery with Battery Components and Balance of Systems
Photos of EACH Installed Battery
BESS Balance of Systems
Note: Not required if no battery is installed.
Photos of EACH Array (max: 10)
Note: All information provided must match the project details in Origin.
Contractor Admin to sign "Conditional Release of Claims"
To be completed by SolarQuote. Please email projectmanagement@seamlessenergy.com
Installation Photos:
Inverter Placard
Installed Inverter
Module Placard
Point of Interconnection
CTs
Array(s)
Optimizer or Micro with serial number clearly readable
Documentation
Initial Permit provided by AHJ
As Buit Planset
Packing slip / Invoice for Equipment (Including Mounting)
Can be requested from directpay@seamlessenergy.com
System Production Pre-Check *(recommended to be completed at NTP)
Design of panels on roof (can be a screenshot of proposal design in SubHub, or screenshot of planset page with panel design)
Installation (M1) Requirements Include:
Site Qualifying Review
Administrative uploads
Design Package Documents
Install Photo Documents
Monitoring Portal Access
Full system activation is required at M1 Submission
This requires the entire system to be installed and turned on to complete commissioning
Any site that is pending interconnection due to MPU, Backup Switch, Meter Collar, etc. will be allowed to proceed without access.
Direct Portal access for the PV System (and Battery if present) is REQUIRED at time of M1 Submission. - KB Article
This requires partners to set up Palmetto LightReach as partners in the platform that you are using - KB Article
Also to configure some of the settings identified in this article.
Key Steps
Ensure full activation and provide monitoring access
Designate Palmetto as system owner
Submit the monitoring ID
Make sure to "Save”
Frequently asked questions:
What does Monitoring Portal Access capture??
Providing the monitoring site ID, sharing direct portal access & maintainer permissions to LightReach is required at M1.
Is maintainer Access Required for M1 Approval?
Only Enphase systems missing Maintainer permissions will result in a rejection. (Look for updates on this topic in the near future)
Expected Inspection & PTO dates will become a M1 requirement starting 5/15/25
Install (M1) Checklist: https://help.palmetto.finance/en/articles/9718783-installation-m1-checklist
Install (M1) Photo Documentation: https://help.palmetto.finance/en/articles/8306274-install-m1-photo-documentation
Final Designs
Final Design Requirement
All deals must include an approved final design document including:
Project Address
Make/model of inverter and module
System layout
System size
Proof of Permit Requirement
All deals must include one of the following:
Authority Having Jurisdiction (AHJ) stamp on the final design (not to be confused with an engineering stamp)
A copy of the permit
Installation Photos
Register the inverter via monitoring portal & grant full access to monitoring@sunlightfinancial.com.
Upload the following photos:
Photo(s) showing each full array on the roof & all installed panels including compass & tilt meter
Photo(s) showing all equipment (Pull back, 10 ft. view) - generators, inverters (or photo of envoy/combiner for microinverters), AC disconnects, utility meter, & production meter (if applicable) with placards visible
Photo(s) showing POI (point of interconnection) to the main service panel or utility meter
Photo(s) showing inverter nameplate (or photo of envoy/combiner for microinverters) with visible serial number
External photo(s) showing utility meter, placard, & full meter number
Photo(s) showing battery, critical load panel, & EV charger, if applicable
Select and submit equipment
Enter Annual Production
Upload corresponding inverter info and documentation
Please refer to the inverter mfg. listed in Table of Contents
Signed Job Card (or finaled permit)
Full Building Permit - Only required when the finaled permit or signed job card does not contain all of the permit details.
COR: Close-Out Report (installation pictures)
Materials Invoice: Listing Model #'s/SKUs (Seamless team to upload)
Resources: M1 – Substantial Completion
Enter Equipment Information
a. Confirm or update the system attributes and submit the Equipment Information form in Partner Portal
i. If material or layout changes are made, please update the design in Aurora to verify if a change order is required prior to submitting for M2.
2. Installation Photos
a. Please see EnFin Design Standard and Installation Photo List in the Partner Portal Resources
3. Approved Permit (Building / Electrical)
a. Approved Permit must include customer identifying information (Name / Installation Site Address)
b. Permit must include accurate scope of work
c. If no permit is required by AHJ, please upload supporting documentation
4. As Built / Change Orders:
a. Revised Design Package, Proposal, and Shade Report
PTO Granted Date (will be entered in Subcontractor Hub under "GoodLeap Financed Projects")
PTO Verification Case - documentation required:
Proof of Interconnection (PTO Letter)
Registration and System Setup in Inverter Portal
Proof of Interconnection - documentation required:
PTO letter
Subject property address
Interconnection date
Letter or email was issued by the utility
If your utility does not provide a PTO letter, please provide:
Photo of bi-directional meter, or
Photo (or screenshot) of homeowner's utility portal showing net metering.
Registration and System Setup in Inverter Portal
Enter the Monitoring ID
Upload a screenshot from the inverter monitoring software portal that includes:
Subject property address
The site ID
Contractor Admin to sign "Final Release of Claims"
a. To be completed by SolarQuote. Please email projectmanagement@solarquote.com
System Activation Validation
a. Registration and System set up in Inverter Portal
i. Enter the Monitoring ID found on the inverter (Ex. Solaredge: Site ID; Enphase: System ID)
ii. Please ensure ownership of this site is assigned to monitoring@goodleap.com. Failure to make GoodLeap the owner will result in the case being returned to you and cause delays.
iii. Please upload a screenshot (or take a photo of your screen) from the inverter monitoring software portal. We need to see:
Subject property address
The site Id
Please also ensure that the site has been created, the equipment is mapped appropriately in the software, you've assigned ownership of the site to monitoring@goodleap.com, and the inverter(s) are active with no alerts.
Failure to assign GoodLeap as the owner will result in the case being rejected and funding getting unnecessarily delayed.
Proof of Interconnection
Please upload a copy of the PTO letter. We need to clearly see:
Subject property address
Interconnection date
Letter or email was issued by the utility
If your utility does not provide a PTO letter, please provide:
Photo of bi-directional meter or
Photo (or screenshot) of homeowner's utility portal showing net metering
Final Inspection Permit
Please provide us with a copy of the inspection permit for this project. We need to clearly see:
Subject property address
Final inspection date
Indicator inspection has passed
Interconnection Application/Agreement
a. The Interconnection Application or Agreement is the document submitted to the utility to request interconnection to the grid.
b. In order to receive permission to operate from the utility this application/agreement must be completed and executed by the respective parties, and then submitted to the utility for review.
Activation (M2) Requirements Include:
Monitoring Portal Access (will become a M1 requirement on 5/15)
PTO Documentation
Incentive Documents (If Applicable)
Extended Warranty Documentation (If applicable)
Monitoring Portal Access (M2): https://help.palmetto.finance/en/articles/8306383-monitoring-portal-access-m2
Incentive Deliverables: https://help.palmetto.finance/en/articles/9085138-incentive-deliverables-m2-milestone
M2 Site Improvement Photos (if applicable): https://help.palmetto.finance/en/articles/10012401-m2-site-improvement-photos-if-applicable
Permission to Operate: https://help.palmetto.finance/en/articles/8383543-permission-to-operate
The customer must confirm before you may submit for PTO.
Required Documentation: Approval Letter
Must include: Utility communication showing system commissioned & PTO achieved. Acceptable documents include:
1) PTO letter of approval;
2) Email stating meter set, commissioned, interconnected, or finalized; or
3) PDF of recent bill indicating credit for solar. Note that customer address should be included.
Certify Final Completion in the Concert Portal
Upload corresponding inverter info and documentation
Please refer to the inverter mfg. listed in Table of Contents
PTO Approval Letter
If the Utility for a project does not provide PTO letters, we will require proof of inspection.
Certify Final Completion in the Concert Portal
Upload corresponding inverter info and documentation
Please refer to the inverter mfg. listed in Table of Contents
Finaled/Signed inspection card (required for Propel program)
PTO Approval Letter
PTO Letter: From utility, must show customer address and PTO date
System Monitoring
Performance review
This is to determine if liability exists to our 3rd party with regards to production guarantee.
At least 5 days of production history is required for the performance review.
Total lead time is around 4-7 business days
Final Inspection Card (FIC)
a. The file uploaded is the FIC for this account
i. Please combine with Approved Permit if customer identifying information is not available
b. Permit number matches the permit on file
c. Building or electrical field has inspector signature or initials and is dated
2. PTO (Permission-to-Operate) Letter from Utility
a. Letter must include installation address and PTO date
3. Fully Executed Interconnection / NEM Agreement (or Application)
a. Agreement / Application information must match the PTO Letter (Address, Utility ID, etc)
4. Rebate Reservations (if applicable)
a. If project is eligible for rebate program, please provide proof of rebate reservation
5. System Monitoring Site Access and Proof of System Activation
a. The system is commissioned, activated/producing, and communications online.
i. Please provide screenshot of system production from monitoring site
b. Monitoring site ownership is transferred to EnFin
i. Monitoring Site Access Guidelines can be found in the Partner Portal Resources Page.
6. Inverter Warranty Extension (SolarEdge only)
a. Extended warranties to 25 years required where applicable. Maximum extended warranty required.
i. SolarEdge extended warranty required