GoodLeap:
Jobs must be installed 30+ days AFTER NTP is granted.
PTO date from utility must be AFTER the installed date. Doing so may result in project cancellation and net funding.
LightReach:
PTO cannot be requested from the utility until LightReach grants "PTO GreenLight Approval". Projects that receive PTO before this designation may be ineligible for funding, and the disbursements may be withheld or net funded.
EnFin:
PTO cannot be requested from the utility until the project has reached the status of "Ready for M3" by EnFin. Projects that receive PTO before this designation may be ineligible for funding, and the disbursements may be withheld or net funded.
Extension Policy: An extension can be requested to projectmanagement@seamlessenergy.com
The following criteria must be met:
Approved final Inspection(s) completed
Net Metering/PTO Application has been submitted
Request must include:
Explanation of delay
List of remaining items necessary to achieve PTO
Expected date of completion
Seamless Energy will coordinate with the financiers directly in efforts to obtain the extension, and update the Subcontractor Hub platform with all project updates.
ALL PROJECTS:
DirectPay material costs will be NET funded 14 days after "ship date" (delivery of materials) -- NO EXTENSIONS
LightReach:
DirectPay material costs will be NET funded 30 days after Installation SUBMISSION, if no install milestone approval received
Installation Milestone + DirectPay material costs will be NET funded 115 days after Installation APPROVAL, if no Activation Milestone approval received
GoodLeap:
Installation Milestone + DirectPay material costs will be NET funded 180 days after Installation APPROVAL, if no Activation Milestone approval received