The task list below (Table 2) is split into project phases or milestones (in Bold) with estimated effort in hours, and number of days allowance. The days allowance takes into consideration that work will by typically carried out on weekends, and outside my day job working days.
The timetable is dynamic, if tasks become overdue I will highlight them red. The progress blog under section 9 will contain updates if and when a task breaches deadlines against the initial plan, with a description of the mitigation measures to return back to schedule. All completed tasks will show in green and orange as in progress.
Table 2 - Task List