Status:
Design decisions have all been finalized and final prototype fabrication has been started. Components for the spar base are being manufactured and welded by the campus machine shop. The essential parts needed for project production, such as the 6” PVC pipes and couplings, have been acquired. Production schedule is on track and the team is now prioritizing the construction of the spar mooring. Secondary critical items, such as fastening materials, will be purchased this week to be added to the final prototype. Hardware testing methods are being finalized and will be conducted on the prototype during week 9 to ensure proper performance for the final design review presentation for the sponsor on week 10.
Accomplishments from Previous Week
Critical components were purchased and final prototype fabrication was started
Corrections from TA/instructor comments were made on Final Report
Miniature scale model was tested in different settings
Began working on the preliminary design review Presentation
Spar base design was finalized and parts were dropped off at machine shop for fabrication
Full design was approved by sponsor and secondary goals are now being addressed such as developing spar handles for divers and other additions to the prototype
Goals for Next Week (list names after each item).
Improve and update Final Report and finish the 2nd draft (Team)
Perform updated FEAs with all final component properties and imposed forces (Eliran Quentin)
Retrieve manufactured parts from the machine shop (Erik Zamarripa)
Purchase all secondary components and tools (Quentin and Erik)
Manufacture and assemble the final design prototype (Erik Zamarripa & Ayesha Riaz & Eliran Lenard)
Format final version of website and finish executive summary (Horim)
Sponsor Comments from Last Meeting (Zoom meeting 2/16/21)
Final spar base design was discussed and approved
The use of plain-end pipes with PVC couplings instead of rubber hose clamp connectors or bell end pipes was addressed and approved by sponsor for the final design
Concerns of using galvanized stainless steel due to the zinc content which would also pose a problem for welding. Hot-dipping the manufactured steel part was recommended to solve the oxidation problem in the ocean. Hot-dipping shops are being explored to address the issue
Emphasized the importance of finding the deflection/bending of the spar. Discussed the beam equation and how it was used to find the moments and the stresses at joints and deflection of the spar. He found the analytical methods appropriate and encouraged the use of the beam equation analysis to quantify how the spar will behave when deployed
Concern of breakage, look out for the material limits, yield and tensile strength
Instructor Comments from Last Meeting (Zoom meeting 2/16/21)
Analyzed the pros and cons of the material of the spar we are planning to use. Stainless on stainless is a problem that is going to be addressed with a lubricant or loc-tite for threads. Also suggested the use of cotter pins for holding the hinge pin in place
Clarified analysis with the beam equation and MATLAB plots for stress and displacement of spar with guy wires attached at 5m and at 5*sqrt(2)=7m, as well as the moments and slope plots
Was updated on final design of the base and the parts need that need to be fabricated/machined by Tom
Comments from Other Students in the Class (Presentation review comments)
Their simulations/analysis were pretty well done, I felt as though they had done enough simulations to know the effects of their worst case scenario
The explanation of why the previous version doesn't work is good
Clearer diagrams this time
You guys seem to have a very solid grasp of both the problem and your solution
Clean CAD models and design layout! It was visually appealing
Schedule
Describe upcoming milestone
Manufacture/assemble the final design of the prototype (2/13 - 2/25)
Quality control/test the final design (2/26- 3/2)
Update Gantt chart.
- Final CAD design approved by sponsor (02/18/2021)
- Manufacture/assembly of the final design (02/30/2021)
- Receive the all parts from machine shop (02/23/2021)
Budget (list amount spent and amount remaining)
Team has spent ($418) out of the $1000 budget limit
Supplier: Industrial Metal Supply Co.
Purchased by Eliran Q. Lenard
GSP200
Galvanized Grade A pipe 2 IPS X SCH 40 ASTM-A-53 GRADE A GALV
Store Cutting - Band Saw
Tolerance (+) 0.063, Tolerance (-) 0.063, Size: 12” 1 piece
Qty (1), Total: $13.87
GSP250
Galvanized Grade A pipe 2 1/2 IPS X SCH 40 ASTM-A-53 GRADE A GALV
Store Cutting - Band Saw
Tolerance (+) 0.063, Tolerance (-) 0.063, Size: 12” 1 piece
Qty (1), Total: $19.87
DHCPN8212RR
8”x 2- 1 / 2”, Black Pneumatic, Rigid Plate Caster, Load Capacity 350 lbs,
DH,(CPN8212RR) 5.30lbs/ea
Qty (1), Total: $26.80
Supplier: Imperial Sprinkler Supply
Purchased by Eliran Q Lenard
600-040 PIPESW 6”
SCH 40 PVC” PIPE Total: $207.93
429-060 FTGS40 (x5)
COUPLING Sc h40 PVC total: $101.41
RHB-PT
GLUE RED HOT BLUE GLUE LOW VOC total: $15.10
Taxes: $17.29
Total: $341.73
Supplier: Home Depot
Purchased by Erik Zamarripa
1x 2ft 2'' ABS pipe, total: $3.87
1x 2ft 3'' ABS pipe, total: $7.97
1x 2ft 4'' ABS pipe, total: $9.97
Progress on Report and Webpage
In progress
Continue working on the final report - Second Draft week 8
Update analysis figures such as FEAs and MATLAB plots
Chapter 4 needs particular attention to better explain major components
Webpage has been updated
Week 8 progress report
All project files need to be uploaded that include purchased parts list and their specification sheets, CAD files, and MATLAB code
Executive summary needs to be linked on home page
Ensure all figures and images have proper descriptions and are addressed on final design page