Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finalized frame design and began sending designs to machine shop.
Initial version of GUI developed to control the 3D Magnetic Control System.
Created first prototype of C-bar magnet
Basic mathematical calculations for the
Will begin manufacturing solenoid and cutting out parts
Accomplishments from Previous Week
Created a GUI to control the 3D Magnetic Control System.
Prototype C-magnet with 170 wrappings
Created Toolpath for transformer inspired solenoid (and dropped off stock to be machined)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finalize GUI after getting feedback from the project's sponsor (Tanner).
Fit frame and conduct a full assembly of parts (CAD)
Create toolpaths for Tom to machine
Continue creating toolpath for anything that needs CNC and design spool-like structure to slide coils easily (John)
Wrap machined iron cores with coil (design prewrapping jig) (Joseph)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Not applicable.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Reach out to Campus Research Machine Shop for welding (Chris)
This may no longer be applicable if we proceed with non-welded magnets
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Not applicable.
Risks and Areas of Concern
Welding/fusing strength of iron core return path structure for C-bar inspired design.
Viability of C-shaped magnet design. Initial testing revealed that this design does not produce as strong a magnetic field as originally believed.
After using basic calculations, the issue is strongly linked to Iron Core purity
Ensuring that the final system is safe (i.e. in regards to electrical, heat, etc. concerns).
Resources or Information Required but not Available
Not applicable
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
To date, the team has spent $469.69 which leaves a budget of $30.31 left.
Progress on Report and Webpage
In the process of implementing changes recommended by instructor on the report and webpage.
Updated the webpage with Week 7 Progress Report information.