Overview of Status of Analysis, Design, Fabrication, Tests, etc.
All key components designed
Key hardware: frame, electromagnet coils and cores, must be machined and assembled
C-shape core donut designed
Accomplishments from Previous Week
Design new iron core geometry to accommodate return paths
Updated Frame designs to accommodate scope change and new geometric constraints of new core geometries
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Have iron cores machined, and assemble 4 transformer inspired solenoids (Joseph)
Work on controls system GUI for Arduino (Tanner).
Continue design changes to solenoids and overall design. (John)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
No sponsor comments since the team's scope change
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
From last Proof of concept presentation (2-4-21)
Reaching out to Professor Fullerton for meeting on magnet design -> We are waiting to test our current prototype to better engage with the Professor on further improvements.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None received.
Risks and Areas of Concern
Welding/fusing strength of iron core return path structure for C-bar inspired design
Is welding available?
Ensuring final system electrical safety
How wide are the machine tools? Will it be small enough to fit into our design?
Resources or Information Required but not Available
Actual efficiency of C-shaped magnet. Currently, the team is testing the current design and reaching out to Professor Fullerton for additional advice.
Waiting on response from Fullerton once Prototype C-magnet is built.
Schedule
Describe upcoming milestone
Test C-shaped (donut) solenoid (end of week 6)
Assemble modular solenoids (end of week 7)
Assemble frame and attach solenoids (end of week 8)
Update Gantt chart.
Budget (list amount spent and amount remaining)
To date, the team has spent $353.79 which leaves a budget of $146.21left.
Sponsor maybe able to supply more funding if necessary
Progress on Report and Webpage
Webpage is in progess