Overview of Status of Analysis, Design, Fabrication, Tests, etc.
All the parts are cutout, began assembling the project
Pre-wrapped 20awg wire and tested the magnetic intensity
Finalized GUI
Final checking and wrapping up the project
Documentation of engineering drawings; User Manuals; Bill of Materials
Accomplishments from Previous Week
Frame components machined and assembled.
Pre-wrapping jig used to tightly wrap solenoids.
Tested GUI with the fully assembled frame and solenoids.
Documented frame design drawings and CADs
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Test and improve GUI (Tanner and Joe).
Documentations and engineering drawings (John)
User Manuals on assembling (John, Everbrook)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor wants 2 CAD models: 1) Transformer Solenoid Top/Bottom 2) C-bar electromagnet
Wants an easy to understand manual on how to assemble the frame.
Sponsor approved budget increase to $700.
Happy with how the GUI looks and is intended to work.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Not applicable.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Not applicable.
Risks and Areas of Concern
Ensuring that the final system is safe (i.e. in regards to electrical, heat, etc. concerns).
Heat from the wire melts PLA and Electrical Tape
3D Printing Deadlines
Final Workspace needs to be printed
Resources or Information Required but not Available
Not applicable
Schedule
Describe upcoming milestone
Test the structural integrity
Finish Documents, Bill of Materials, User manuals (3/12/21)
Final Design Review with the sponsor (3/12/21)
Budget (list amount spent and amount remaining)
To date, the team has spent about $615.23 out of a budget of $700 which leaves $84.77 remaining.
Progress on Report and Webpage
In the process of implementing changes recommended by instructor on the report and webpage.
Updated the webpage with Week 10 Progress Report information.
Uploaded new, higher quality pictures to the team website.