Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Edited co-fired design to Sorin's specifications
Gave Sorin's information to our sponsor for future reference
Gave Marcio's information to Oasis for future reference
Prototype design tested at SPAWAR
Results: Chip cooled to 9K instead of 4K
Due to thermometer placed on PCB instead of directly on chip
Accomplishments from Previous Week
Visited SPAWAR and gave sponsor our prototype to cool down to 4K
Gave presentation of final design to sponsor
Completed Report full with updating drawings and prototype testing results
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finalize Poster
Add more drawings and remove lengthy text
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Asked if we could potentially add 2 more pin outs to connect to the pins on the side of the chip?
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
No budget changes this week
Turned in all reimbursement forms
Progress on Report and Webpage
Report & Website final draft complete and uploaded to website