Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Individual Component Analysis complete.
Risk Reduction testing for off-loading system complete.
Full CAD mockups made of system.
Accomplishments from Previous Week
Individual Component Analysis complete.
Risk Reduction testing for off-loading system complete.
Full CAD mockups made of system.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Risk Reduction presentation.
Meeting with sponsor on Thursday (unless canceled due to Coronavirus).
Analyze feedback from other groups and from instructor.
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comment: pleased with risk reduction testing.
Comment: need safety briefing to work in space.
Action: completed safety briefing.
Comment: can utilize company resources for sourcing materials, machine shop work.
Action: met the relevant ReoTemp people.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
3/10/2020 meeting w/ instructor
Comment: Remember to utilize materials that the MAE department has on-hand, especially for prototyping.
Comment: PTFE will be the lowest friction material option.
Action: did for risk reduction & individual component analysis.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Potential implications and delays due to coronavirus.
Resources or Information Required but not Available
Uncertainty about next quarter.
Schedule
Gantt chart is updated.
Budget (list amount spent and amount remaining)
Spent: $1050
Remaining: $8950
Progress on Report and Webpage
Gantt chart and finances pages have been updated.