Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Controls - almost there
Buoyancy- getting there
Accomplishments from Previous Week
Replaced electrical components after a small "fire" in the dry bay
Completed a figure 8
Printed new ducts
Coated the X-mount and the new ducts
Got wifi working
Set up a swimming pool behind the machine shop
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finalize weight and balance -Sam
Finalize controls - Matt
Finish the report - All
Finish the Poster - Sam and Steve
Finalize the Visual tracking - Steve and Nelly
Finalize wiring - Nelly
Finalize Web Page
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Don't get too distracted with the visual tracking- make sure the controls work
We got a figure 8 which satisfies the functional requirements
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
"Setting up a pool is taking it too far" - Sam's room mate
No it isn't
Risks and Areas of Concern
Electrical gremlins getting in the way
Leaking of the 3-D printed parts
Schedule
Finishing everything
Budget (list amount spent and amount remaining)
Spent: $1565.90 Remaning: $934.10
Progress on Report and Webpage
Submitted the drafts