Overview of Status of Analysis, Design, Fabrication, Tests, etc.
First Prototype done and tested
Accomplishments from Previous Week
Prototype put together-all components fit
Assembled new battery bay
Completed Straight line test
High under water camera resolution-Prototype does not need Done
A spreadsheet to track buoyancy has been made and mass measurements have been taken
Ducts and the X-mount were reworked to get to the right buoyancy
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Sam:
Buoyancy Analysis
Implementation of ducts
Matt:
Re-size the tube
Continue working on drivers
Steve:
Continue work on the camera
Janelle:
Complete wiring Schematic
All:
Mechanical Optimization
Code Dynamics and Visual Feedback
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comment:
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comment: You're on track for an A, but you can blow it with the report
We won't blow it.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Wow, that looks cool
Wow, that looks ugly
Risks and Areas of Concern
Hydrophone test will probable not be carried out, but prototype is relatively silent to human ears
Resources or Information Required but not Available
We got this.
Schedule
Next Week:
Coding
Update Gantt chart Here: https://docs.google.com/spreadsheets/d/1T9f8QqgFpOAlexk3_7_bvZPCjwls06H0xiEhNaZfJvo/edit#gid=0
Budget (list amount spent and amount remaining)
Spent: $1,365.59
Remaining: $ 1134.41
Progress on Report and Webpage
Completed Week 8 update