Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Deciding upon the conceptual design of the fish
Accomplishments from Previous Week
Completed rough drafts on Individual Component Analysis on camera selection, propulsion, power requirements, and attitude determination of the vehicle.
Completed generalized dynamic model of vehicle
Established most design specifications based upon FR’s
Generated design concepts
Spoke with Dr. Popper
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Complete Individual Component Analysis - All
Begin overall design- split work after conceptual design is decided upon
Begin Purchasing components - All
Parameter prediction for Model - split work after conceptual design is decided upon
Lay down software architecture - split work after conceptual design is decided upon
Fill out reimbursement forms - All
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
The last meeting was canceled. Meeting on Thursday before Professor meeting.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Keep working towards risk reduction so that you can be ready to hit the ground running in Spring Quarter
Pushing towards design
Risks and Areas of Concern
That we can’t make the jump from conceptual design to actual design this week
Motors that we’re considering going out of stock.
Heading angle determination
Resources or Information Required but not Available
Google has been on our side so far
Schedule
Picking the general design direction by April 1st
Updated Gantt Chart https://docs.google.com/spreadsheets/d/1c1CFlDvkosC8mgAtC04owfGsOqRf6CXGE960jZ44mBw/edit?usp=sharing
Budget (list amount spent and amount remaining)
Spent $ 119.80
Remaining: $ 2380.20
Progress on Report and Web page
Drafts of Individual Component reports are complete