Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Nearly all parts have arrived
Assembly and manufacturing in progress
Preliminary software writing in progress
Accomplishments from Previous Week
Configured Raspberry Pi OS and important settings
Conducted tuft Test successfully
Conducted Motor Characterization tests
Dry bay tube machined and initial assemble begun
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Matt:
Help with dry bay assembly and motor tests
Get PWM working with PWM board
Get IMU working with Raspberry Pi (High Priority)
Sam:
Print final plug mount
Print External motor mount
Steve:
Finalize Propeller design
Conduct Hyrophone test
Record video with R-Pi camera
Janelle:
Finalize wiring
Dry bay seal test
All
Straight line test
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor traveling around Europe for the next few weeks.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Keep working hard, looks good
Risks and Areas of Concern
Printing upstairs is a huge hassle.
IMU drivers are difficult to work with.
Resources or Information Required but not Available
Computer science genius
Schedule
Milestones
Finish Assembly
Straight line test
Update Gantt chart:https://docs.google.com/spreadsheets/d/1T9f8QqgFpOAlexk3_7_bvZPCjwls06H0xiEhNaZfJvo/edit#gid=0
Budget (list amount spent and amount remaining)
Spent: $881.38
Remaining: $1618.62
Progress on Report and Webpage
Updated Week 5 update