Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Considering design utilizing 3-D printing and rotating shafts seals
Research on what disturbs fish is wrapping up
Beginning test phase for leaking through 3-D printed parts and shaft seals.
Accomplishments from Previous Week
Risk Reduction Tests have been selected.
Pressure test tank has been procured.
Specimen for Risk Reduction have been selected and are being designed.
Materials for Risk Reduction Test have been purchased.
Research on what disturbs fish has been completed.
Steve’s 3-D printer has been calibrated
Reached out to Sponsor to talk to Scripps engineers
Reached out to Dr. Popper, an expert on noise disturbances to fish, got a reply
Wrote Test Procedure and Conditions for passing for leak test under pressure
Analysed muscle wire
Created a model based upon aircraft equations of motion
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Complete Design and Manufacture of 3D printed elliptical cylinder - Matt
Complete Design and Manufacture of 3D printed tube w/ threads - Janelle
Aid in manufacture - Steve/Sam
Test Specimens - All
Prepare Final Presentation - All
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Paraphrased from sponsor: Discuss with my engineers about anything related to “building.”
We discussed and learned from his engineers on staff.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Paraphrased from Dr. Hoople: Narrow down risk reduction (RR) and work towards those
We decided that our RR will be on leaking through porosity and rotating shafts, and through research of what disturbs fish.
Paraphrased from Dr. Gillete: Look into Muscle Wire
We researched it and did some basic analysis for its use on a control surface.
Risks and Areas of Concern
That the measures we have chosen to stop leaking won’t work
Not being able to measure sound intensity under water
Resources or Information Required but not Available
Procuring enough information to produce specs regarding fish disturbances to validate “minimal Disturbance.”
Schedule
Completion of Risk Reduction Tests
Complete the Presentation due next Tuesday
Budget (list amount spent and amount remaining)
Spent: $ 119.80
Remaining: $ 2380.20
Progress on Report and Web page
The webpage has been created.