Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Internal and external main structures have been printed
External extructure has been assembled
Internal structure is currently being assembled
Preliminary software writing in progress
Accomplishments from Previous Week
External structure printed and assembled
Battery design complete, assebled and tested
Raspberry Pi protoboard designed finilized
dB Threshold for sound has been found
Dry Bay passed seal test
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Matt:
Get PWM working with PWM board
Get IMU working with Raspberry Pi (High Priority)
Sam:
Print final plug mount
Design Ducts
Steve:
Finalize Propeller design
Conduct Hyrophone test
Record video with R-Pi camera
Janelle:
Finalize Wiring Assembly
Finilize Assembly of Dry Bay
Record video with R-Pi camera
All
Straight line test
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor traveling around Europe for the next few weeks.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Keep working hard, looks good
Risks and Areas of Concern
Communication with sensors
IMU drivers are difficult to work with.
Resources or Information Required but not Available
Computer science genius
Schedule
Milestones
Finish Assembly
Straight line test
Update Gantt chart:https://docs.google.com/spreadsheets/d/1T9f8QqgFpOAlexk3_7_bvZPCjwls06H0xiEhNaZfJvo/edit#gid=0
Budget (list amount spent and amount remaining)
Spent: $881.38
Remaining: $1618.62
Progress on Report and Webpage
Updated Week 6 update