Spring Milestones
Our project's timeline consists of the following milestones that were set at the beginning of the semester. Click on any milestone heading or deliverable to see deliverable and/or detailed explanations of each portion of the project.
MILESTONE DELIVERABLE DATE
- Trash-Collecting Boom
- Materials Purchased Purchase Spreadsheet 1/31/2018
- Buoyancy and Collection Testing Images from testing 2/14/2018
- Boom and Collector Implemented On-Site Proposal and Permit Application 2/28/2018
- Pump Screens
- Materials Purchased Due to unforeseen circumstances these 1/31/2018
- Performance Testing milestones were never completed 2/14/2018
- Implementation on-site 2/28/2018
- Dredging
- Plan/Calculations Elevation Raster and Dredge Volume
- Cost Estimate General Prices and Final Cost Calculation
- Stream Restoration Design
- Site Survey Survey Data and Elevation Maps 1/31/2018
- Stream Design Perspective and Plan Views of Design 4/1/2018
- Design Details Plan and pictures for Riparian zone/misc. structures 4/1/2018
- Cost Estimate Cost calculations and final estimate 4/4/2018
- Concept Art of Finished Area Incomplete due to failed plans with Landscape Architect 4/11/2018
- Neighborhood Feedback
- Meeting and Opinions from Homeowner's Assoc. Powerpoint, Handout, and Results from April Meeting 4/25/2018