District: Uptown - Partial
Owner: Archie Casbarian
HDLC Staff: Jesse Stephenson
Rating: Contributing
Applicant: Adrienne Casbarian
Description: Retention of the demolition of more than the approved scope of work at a Contributing rated, 1-1/2 story, single-family residential building in deviation of a Certificate of appropriateness.
HDLC Guidelines:Â
Section 12, Pages 23-24 of the Guidelines for New Construction, Additions and Demolition, state that the demolition of all or portions of historic resources within a local Historic District or Landmark site are considered drastic actions, since they alter the character of the area. Once historic resources or buildings that contribute to the heritage of the community are destroyed, it is generally impossible to reproduce their design, texture, materials, details and their special character and interest in the neighborhood. As a result, the HDLC rarely considers the demolition of Significant or Contributing buildings or structures within a local Historic District or on a Landmark site to be an appropriate option.
Retention Items:
Demolition beyond the approved scope
Fine Range: $1,000-$90,720.Â
Staff Recommendations:Â
In 2020 an application was filed to remove 100% of the existing roof and more than 50% of exterior walls. Â This eclectic style raised basement home was constructed sometime between 1920 and 1930, within the period of significance for the local historic district. HDLC Staff recommended the denial of the application. At the Commission meeting held May 6, 2020 the Commission was unable to reach a majority decision resulting in a de-facto denial. An appeal was made to New Orleans City Council and the demolition of 100% of the existing roof and more than 50% of exterior walls was approved on June 18, 2020.
On February 23, 2023 visual inspection by HDLC Staff noted that the current demolition exceeded the approved drawing set. A stop work was not issued and the General Contractor and Owners were notified immediately by HDLC Staff. In the course of the discussions another in-depth inspection was requested by the applicant and performed by HDLC Staff.
The conditions at the front façade were poor and had a mixture of materiality comprised of wood, concrete and brick. The mixture of these materials in the way they were used, coupled with termite damage, gave little structural integrity to the walls above.Â
The level of demolition approved by New Orleans City Council was not a tenable reality from the beginning of this project. The Staff recommends the approval of the demolition of more than the approved scope of work in deviation of a Certificate of Appropriateness (CofA).
Case History:
23-07212-HDLC - Application for the Retention of the Demolition of more than the approved scope of work in deviation of a Certificate of appropriateness.
20-22037-HDLC - Certificate of Appropriateness issued for demolition exceeding HDLC Guidelines
06/18/20: City Council overturns HDLC de-facto denial.
05/14/20: Appeal request logged into the City's land management system.
05/06/20: HDLC Commission was unable to reach a majority decision, 5 yay/5 nay, resulting in a de-facto denial.
***ONLY EXTERIOR WALLS HIGHLIGHTED ARE IN DEVIATION