COST RESEARCH
Project title: Design Technology Block
Location: West Midlands
Date: 16-Dec-2019
Building cost: £2,210,461
Cost/m²: £1,444
Floor area: 1,531m2
Main construction: Steel framed
Storeys: 2
Level of analysis: Elemental
Project details:
2-storey the art and design technology block (1531m2) for secondary school together with the demolition of 2Nr temporary classrooms and the existing design technology block, refurbishment of the retained art block (340m2), and external works comprising macadam paving, brick retaining walls, drainage, services, and site lighting.
Site conditions: Works within occupied school site, restricted working space.
Contract: JCT Standard Building Contract 2016 edition
CONTRACT BREAKDOWN
Measured work: £2,445,133
Provisional sums: £80,325
Preliminaries: £182,231
Risk (client's contingencies): £133,000
Contract sum: £2,840,689
Ground floor: 766m2
Upper floors: 765m2
Gross floor area: 1,531 m2