Weekly Progress Reports should be printed out before meetings with the sponsor and instructor.
All team members should be able to explain all items on the progress report.
To start a new progress report, create a new webpage and use the Progress Report Template.
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Budget at UCSD is $500.00 ($279.15 already spent). Budget at SPAWAR is $5500 ($2916.03 Spent)
Track and drive shafts/wheels arrived. Most Idler wheels have arrived, but still missing 4. (Ryan)
Track has been cut and belt lacings have arrived, but awaiting final assembly to measure and cut track (Ryan)
Frame and chassis designs in fabrication. Main track plates already cut. Chassis bars already cut, but need to be welded. (Mike & Edrees)
Track Tensioner is fabricated and assembled. Awaiting assembly into full design. (Ryan)
Able to control and drive the Segway. Currently the system wireless. (Edrees)
Segway power cable/hub adapters have arrived and chain sprockets have been welded on. Awaiting final assembly to break and reattach the chain (Mahin)
Custom drive shafts completely machined. Key stock and other components have been attached. Awaiting final assembly to press drive wheels back on (John)
Accomplishments from Previous Week
Received power cable and continued controls testing on Segway Robot (Edrees)
Completed machining of chassis and frame (Mike)
Completed machining and assembly of track tensioner (Ryan)
Machine hub adapters and attach chain sprockets (Mahin)
Completed machining of drive axles (John)
Revised and updated project report (All team members)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
More Website Updates/Construction (Edrees, Ryan)
Perform speed and torque tests on Segway robot. (Edrees)
Finish machining brackets for track plates (Mike, John, Ryan)
Weld Chassis bars together (Mike)
Measure track length required and splice tracks together (Ryan)
Final Assembly and field test (All team members)
Revise and update project report (All team members)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Final design concepts look good and are ready for fabrication.
Missing idler wheels are an issue. We need to contact the provider and demand an explanation.
Controlling the Segway should require only a wireless controller and a laptop attached to the top of the robot.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Need to meet time constraints!
Minutes to group meetings need to be provided.
Risks and Areas of Concern
Order of idler wheels we received is missing some parts, and some are the wrong dimension. We are in process of contacting the provider, but yet to have a response. We cannot get wheels of the right size nearby, since they are specialty snowmobile idlers. Worst case scenario is we machine some replacements out of aluminum.
Track tensioner locking mechanism is held up by a relatively small shoulder bolt in shear. It is fine for normal operation, but may not survive an impact.
Resources or Information Required but not Available
N/A
Schedule
Update Gantt chart.
Budget (list amount spent and amount remaining)
$6000 provided
$2906.13 spent (Spawar Budget)
$279.15 spent (UCSD Budget)
$2815 remaining
Progress on Report and Webpage
Home and Reports pages reformatted and organized (Ed)
Added links to sponsor and updated Project Management page w/ video embedded (Ryan)
Added links to budget forms and order forms in Budget page. (Ryan)
Added team member info, link to sponsor, and acknowledgements to Team page (Ryan)
Added photos and CAD to Multimedia page (Ryan)
Added presentations and final report draft to Reports page (Ryan)
Added useful provider websites and previous similar senior project webpages to Resources page (Ryan)
Report second draft complete. Reorganization, reformatting, and constant updating still needed.