Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Track type decided (snowmobile parts). Online purchase locations researched (ebay for used, Dennis Kirk for new). Awaiting financial approval...
Initial Frame and Tensioner ideas decided. Initial designs in progress.
Basic force and power calculations complete. Need to purchase and inspect hardware before continuing with more detailed calculations.
Segway basic robotic platform acquired. Not yet disassembled for conversion. Controlling equipment not provided, so we are unable to perform operating tests.
Accomplishments from Previous Week
Researched component providers (John, Mike, Ryan)
Decided on COTS parts, custom parts (John, Mike, Ryan)
Created organized online planner for meeting availability (Mahin)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Meet with sponsor to clarify SPAWAR purchasing protocol. (All team members)
Purchase COTS part (All team members)
Begin feasibility testing. (Ed, Mahin)
Begin design of custom parts based on COTS parts dimensions (John, Ryan, Mike)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Tensioner design was more complex than he expected, but he was willing to experiment with the new idea.
Tracks come in a wide variety, and fiber-reinforced tracks seem like the best option.
Frame and track geometry design can be simple if flat, but have greater climbing ability if angles are used as well.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Goals and expectations should be more detailed regarding expected jobs of each team member
Risks and Areas of Concern
Team members are contributing bits and pieces to all parts of the project. Specializations should be decided immediately.
Lack of reliable meeting times for all team members make cooperation a chore.
Resources or Information Required but not Available
Purchasing protocol (SPAWAR) is still unclear despite who we ask (Isaiah, JV, Aaron). We cannot continue further without purchasing vital components!
Schedule
Update Gantt chart.
Budget (list amount spent and amount remaining)
$6000 provided
$50 spent
$5950 remaining
Progress on Report and Webpage
Initializing