Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Track type decided (snowmobile parts). Budget for UCSD is $500.00 at the current moment and waiting for more information about further funding.
Frame decided and further analysis implemented into design. Tensioner design is pretty much set, unless new ideas provide advantage with proper analysis.
Segway basic robotic platform taken to campus for full access of all team members. Waiting for controls for the Segway and looking to work all dimensions when tracks arrive.
More analysis about the splicing of snowmobile tracks (perhaps scheduling time with Tom to talk about it).
Accomplishments from Previous Week
Created a cleaner website/feasibility (Ed. Siddiqui)
Researched Snowmobile tracks (Ryan)
Purchased drive wheels/drive shafts/tracks (Ryan)
Researched Chain Tensioner Designs (John)
Drive train gear ratio calculations reworked (Mahin)
Researched track splicing and belt lacing (Ryan & Ed)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Send orders for raw materials & COTS parts to Aaron at SPAWAR (All team members)
Begin feasibility testing, Website Updates/Construction (Ed)
Rework designs of custom parts based on COTS parts' dimensions (John, Ryan, Mike)
Rethink track tensioner designs based on sponsor opinion
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Expressed increased support for a single-pivoting bar track tensioner over the barred-link design.
Reiterated that stock Segway parts must be unaltered so that the track kit is reversible
Wanted us to research more into track geometry design to chose a proper lead angle and length
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Discussion of ideas of frame design
Some confusion about purchasing clarified
Risks and Areas of Concern
Purchasing from ebay.com reduces cost immensely, but is difficult to account for in purchasing bureaucracy
Unable to run full-scale tests without a robot controller
Resources or Information Required but not Available
N/A
Schedule
Update Gantt chart.
Budget (list amount spent and amount remaining)
$6000 provided
$270 spent
$5730 remaining
Progress on Report and Webpage
Home and Reports pages reformatted and organized
Added links to sponsor and updated project management page (w/ video embedded)
Beginning report organization