Team 13 – Delta Design – Week 3 Progress Report
Inkyu Kim, Kyoung Kim, Youngjin Kim, Yule Kim
Overview of Status of Analysis, Design, Fabrication Tests, etc.
- Waiting for materials for fabrication, began programming in LabVIEW
Accomplishments from Previous Week
- Ordered materials(pressure regulator valve, Aluminum tube)
- Hooked up RTD to LabVIEW and set up data acquisition and began calibration
- Hooked up fan and heat sink to LabVIEW
- Hooked up Solenoid Valve to LabVIEW
Goals for Next Week(list names after each item). Use Specific and Measurable Objectives
- Order more materials(pressure relief valve, cryogenic hoses, hose fittings) – Young Jin Kim
- Begin fabricating mixing chamber – Everyone
- Make final CAD drawing for Testing Chamber and Mixing Chamber– Kyoung Kim, Yule Kim
- Begin LabVIEW – Everyone
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
- Be careful when cutting aero gel
- Sent us an interesting article regarding testing DUT with only LN2
- Consider building mixing chamber out of aluminum instead of acrylic
- Mixing chamber should be box shaped or rectangular and shouldn’t be too big
Risks and Areas of Concern
- LabVIEW
- Testing chamber design and feasibility
Resources or Information Required but not Available
- Waiting for E-mail response from Praxair regarding LN2 availability
- Cryogenic hose information from Dr. Babcock
- Requested information from National Instruments about RTD calibration
Schedule
- Gantt Chart – Begin Fabrication
- Finish CAD and begin Fabricating this week (if materials arrive). If not, continue programming with labVIEW.
Budget
- Budget used: $504.04
Progress on Report and Webpage
- Updated budget page
- Posted Week 3 progress Report
- Posted Week2 final report draft