Filter the list of Jobs from oldest date by Created Date in the Pending jobs list
Check the Job Type
Solar
Rework
Check the Tags to view the ones that may need immediate scheduling:
Job started need to complete
Material order
Check the Location, group
Check notes for any additional work
Check Material Availability
Check the use of Ladder
Solar Lead Techs are (but not limited to)
Scott, Ron, Pete, & iFE
Solar Residential
We will be allowing 3.6 hrs per KW (kilowat) to install, as a target.
3.6 x 6.6kw system = 23.76 hrs total divide by number of guys on site (3) = 8hrs (Target)
Solar Commercial 12kw +
We will be allowing 2 hrs per KW (kilowat) to install, as a target.
2 x 16 kw system = 32 hrs total divide by number of guys on site (3) = 10.66hrs (Target)
Scott (Solar Operations Manager)
Where possible schedule scott + 3, gives the opportunity to check other jobs as well as train a new team member
Scott: Ryan & Ife + floater
Ron: Jackson / Andre
Pete: Dylan / Brandon J
4 people allocation on:
Large panels + 400 w & big panel lift (big double story)