156B Week 10
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
A working prototype has been created and shown to the sponsor
need to increase weight of gyrowheelÂ
Accomplishments from Previous Week
completed gyroscope simulation
created Draft Poster
completed updated draft of Report
completed peer review of Team 11's report
began researching the best way to implement a heavier gyrowheel
Goals for Next Week (list names after each item). Use specific and measurable objectives.
successfully implement a heavier gyrowheel
present Final Design Review Presentation to class and to sponsor
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
5/29/18 in person:
Prasad would like a thicker string to spin the gyrowheel
Prasad would like us to increase the weight of the gyrowheel
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
we did not meet with the instructor this past week
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
5/30/18 comments on Draft Poster:
use more bullet points, too many words and sentences
use smaller labels for figures
need more numerical results
less words and larger font
Risks and Areas of Concern
increasing weight of gyrowheel might compromise integrity of gyroscope structure
Resources or Information Required but not Available
none
Schedule
Describe upcoming milestone
present Final Design Review Presentation to class and to our sponsor
Update Gantt chart.
Budget (list amount spent and amount remaining)
exact amount still not known - have spent approximately $900
Progress on Report and Webpage
webpage is almost done
still need to implement changes from peer review for report