Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Fabrication and testing
Accomplishments from Previous Week
Flow Meter
Fan Code
LCD Code
Transducer code
Add USB data output
Circuit diagram
Sewing
Attach zipper to vinyl
Test anti-tear sewing methods
Hospital bed (Heja)
Bought bed and mattress from surplus store
Report
Applicable Standards
Report 1st Draft
Analysis of end plates and poles FEA
Catenary analysis of nylon support structure
Add Catenary simulation to proof of concept presentation
Proof of concept presentation outline
Website
First draft of website
Sponsors
Update background
Update objectives
"How it works" summary
Photos of current frame
List of Deliverables
Goals for Next Week (list names after each item). Use specific and measurable objectives.
In Progress / Done
Flow meter/pressure transducer
Documentation (Tim, Cameron)
Sewing
Nylon strap mesh (Scott)
Neoprene seal (Scott)
CAD lower frame (Cameron)
Vacuum System
Buy 3 way valve and adapters for hoses and flow meters (Heja)
Report
Organize CAD drawings for report (Cameron)
"Decision Justification" continue outline (Heja)
Abstract (Heja)
Executive Summary (Heja)
Chapter 2: Description of Final Design Solution (Tim)
Final Design Solution with brief review of requirements (Tim)
Figures/Drawings (Cameron/Tim)
Chapter 3: Design of Key Components
Internal Frame (Scott)
CAD Figures (Cameron)
Fabric (Scott)
Flow meter/pressure transducer? (Cameron)
CAD Figures
Chapter 4: Prototype Performance (Tim/Cameron)
Hold pressure test? Postpone until week 7.
Chapter 5: Design Recommendations and Conclusions (Tim)
Changes to zipper for production design
Format Report (Cameron)
Upload Report (Cameron)
Proof of Concept Presentation
Add Catenary simulation to proof of concept presentation (Scott)
Website
First draft of website (Cameron)
Home Page
Sponsors
"How it works" summary
Photos of current frame
List of Deliverables
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Approval of progress
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Use catenary equation to create a simulation for the nylon tie down straps.
Recalculate bending equation with fixed ends
Created matlab simulation with equation to simulate behavior and provide forces on bed
Calculate bending/breakage of acrylic
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Zipper not as airtight under pressure as expected
Tearing at the seams
Resources or Information Required but not Available
Bed (Arrives Wednesday)
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$984.21 Spent
$4515.79 Remaining
Progress on Report and Webpage
Select sections of first draft of report done
Website home page revised to match report