Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Analysis, design, sewing are done including testing the device
Accomplishments from Previous Week
. Poster and video are done. Delivered the device to the sponsors. The work space is clean!!
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Prepare for poster session (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Had a great time working with us and look forward meeting us again.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Good Job from Dr. Silberman and Dr. T
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
It is a very cool project
Risks and Areas of Concern
worn out of material after many use
Resources or Information Required but not Available
Schedule
N/A
Budget (list amount spent and amount remaining)
$2025.22 Spent
$3474.78 Remaining
Progress on Report and Webpage
It's all up. DONE!!