Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Analysis and acquiring parts.
Accomplishments from Previous Week
Decided on sample parts for fabric dome and internal structural support, tested each material and placed initial order.
Ordered hospital pressure regulator for testing.
Met with hospital nurses to present preliminary design solutions
Set weekly meeting time
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Searching for vacuum pumps online. (Heja, Tim)
Ordering tubes and connection pieces. (Heja)
Sew fabrics, zippers and connection ports. (Scott)
Initial CAD Drawings (Cameron, Heja)
Outer shell (Heja)
Internal structure (Heja)
Pressure regulator (Cameron)
Pump connections (Cameron)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Loved initial design idea
Wanted to know our opinions on vacuum pumps.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Update Gantt chart with sub-tasks
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Vacumm pump strength.
Pressure regulator accuracy.
Resources or Information Required but not Available
Hospital vacuum flow rate.
Hospital heart rate monitor data output format.
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$200 Spent
$5300 Remaining
Progress on Report and Webpage
Report not started
Webpage being updated