Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Trigger for Foot Mechanism
Will be stainless steel latch
Foot Hook
Will be replaced by latch release
Will be optimized for Kayak
Kara has always been the boss
Accomplishments from Previous Week
Report with Instructor/TA corrections
Abstract (Isabel)
Table of Contents (All)
List of Figures (All)
List of Tables (All)
Chapter 1: Project Description (Isabel)
Chapter 2: Description of Final Design Solution (Justin)
Chapter 3: Design of Key Components (Denny)
Chapter 4: Prototype Performance (Joshua)
Chapter 5: Design Recommendations and Conclusions (Caitlin)
Acknowledgments (All)
References (All)
Appendices (All)
Improve Team Webpage (All)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish up putting together/welding Frame (Justin/Denny)
Trigger for Foot Mechanism
Implement hook release prototype (Joshua/Isabel)
Foot Hook
Replace with latch release (All)
Camera Attachment onto pole/sampler
Implement Camera mount (Caitlin)
Preliminary Design Review Presentation by 5/24 (All)
An overview of the project and team's objectives.
A description of the final design and how it meets the project objectives (Justin)
A description of each component of the design (Caitlin)
A plan for completing the design by the Final Design Review (Joshua)
A detailed to-do list of all aspects required in completion of the project. Show:
High Priority to-do items that must be completed. Each such item should have a due date no later than week 9, and individuals responsible. (Joshua)
Second priority to-do items, that will be completed time permitting. (Joshua)
A Gantt chart with task assignment for the rest of the quarter (Joshua)
A plan for testing the design (Denny)
List any concerns that need to resolved (Denny)
Second Draft of Report by 5/26
Abstract (Isabel)
Table of Contents (All)
List of Figures (All)
List of Tables (All)
Chapter 1: Project Description (Isabel)
Chapter 2: Description of Final Design Solution (Justin)
Chapter 3: Design of Key Components (Denny)
Chapter 4: Prototype Performance (Joshua)
Chapter 5: Design Recommendations and Conclusions (Caitlin)
Acknowledgments (All)
References (All)
Appendices (All)
Review other Teams Report and Webpage by 5/31 (All)
Improve Team Webpage (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Goal: improve protocol statewide (time-based) (5/18)
Takes too long to sample large estuaries
Previous sampler is limited to arms length (5/18)
*Kayak is essential* (5/18)
Either (2) kayaks or (1) 2-person kayak
Trigger mechanism (5/18)
Try to avoid something spring loaded
Options include: rope, Lokklathc, barrel release (I hook)
Updates (5/18):
Splitting into two pieces
One goes into water and the other one stays on land
We need ~4in + sediment
Ocean Instruments (5/18)
Talk to manufacturer
Contact information from kara
Other (5/18)
Longer rod
Spring constant kx
We can modify one sampler
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Replacement for Wire Hook (5/17)
Lokklatch
Is it easy to mount?Safer?
3D drawing would be helpful
Consider triggering both latches at the same time (5/17)
No optimization needed on "cutting" edge since the cylinder is beveled (5/17)
Camera (5/17)
Mounting, illumination issues
Presentation is graded based on (5/17):
Content
Easiness to be understood
Oral Communication
No "uhhh", "ummm"
Metric Units (english units in parantheses)
Annotated figures
Bullets-not sentences
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Team discovered at the last sponsor meeting that this was Kara's project and that it has to be optimized for kayak use
Team can no longer assume that frame could be used on land/jon boat
Team might have to redesign some components(Downscale) for kayak use which might take more time
Resources or Information Required but not Available
Manufacturer Contact Information
Schedule
Improving Prototype for the next two weeks with addition of some key mechanisms
Foot Trigger Mechanism
Replace Foot Hook
Pole Attachment and 0.1 meter hard stop
Camera Attachment to Pole
Next Draft of Report/Website due Friday, 5/26
Review other Teams Report and Webpage by 5/31
Update Gantt chart.
Budget (list amount spent and amount remaining)
$448.80 spent, $551.20 remaining
Progress on Report and Webpage
Project Management up to Week 8 complete on webpage by 5/24
Report with Instructor/TA edits completed by 5/19