Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Pole Requirements
Between 1.8-3 meters
Sponsor said extension mechanism can be twist lock, push button, or pin
Should be able to withstand 90-180 Newtons of Force
Vibration Motor
New Solution: Slide Hammer
Sponsor said that we should omit vibration motor and implement slide hammer
Frame
Prototype Construction Underway
Capture
Image capture might be difficult due to the random levels of water clarity
Sponsor stated that video might be better idea to allow capture of specific frame when water is clear
Testing Condition Updates
Sponsor Stated that a Jon boat might be used instead of kayak
Sponsor Stated that testing will most likely occur with teams of two people
Prototype Testing will occur on Friday 5/1
Accomplishments from Previous Week
Order Placed for Delrin, Drawer Slides
Order Placed for Waterproof Light, 2nd Camera, 2nd Case (Caitlin)
Order Placed for Sample End Caps (Denny)
Requested Aluminum from Metal Supply (Joshua)
Impact on Society (Isabel)
Finish Readjusting CAD model (Joshua)
Redo Linear Slider Analysis (Justin)
Look into different types of viable collapsible poles (Denny/Isabel)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Analysis:
Slide hammer on Pole (Denny/Isabel)
Camera Mount (Caitlin)
Welding Aluminum (Josh/Justin)
On Kayak Testing to Occur on 5/1
Finding a Suitable Pole (Denny/Isabel)
Finish Prototype Frame (Justin/Joshua)
Design Finished by Tuesday 4/25
Manufacture from Wednesday 4/26 to Thursday 4/27
Integration: Thursday Evening
Sections of Report due on Friday 4/28
Applicable Standards (All)
Get Started on Proof on Concept Presentation (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor Stated that a Jon boat might be used instead of kayak 4/17
Sponsor Stated that testing will most likely occur with teams of two people 4/17
Sponsor Preferred Slide Hammer in place in Vibration Device 4/17
Team has decided to omit Vibration Device at the current time
Sponsor Stated that when foot is removed after taking a sample the sediment would sometimes slide out due to lack of sealing 4/24
Team is brainstorming solutions such as method of draining seawater from sample tube to decrease weight of sample before sealing
Sponsor has identified location for testing of sampler device - Liberty Station NTC Park, the north end has a boat launch with sufficient sediment 4/24
Recommended Go-Pro with 360 Degree instead of multiple cameras 4/17
2nd camera was already bought
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Should test/analyze scooping mechanism on actual algae to observe is mechanism is adequate for the job 4/19
Testing will be done on Friday 5/1
Slider analysis to determine if feasible 4/19
Try to make slider as big as possible
Try to make sampler weight in water as close to 0 N as possible
More slider analysis was performed and design was updated
Recommended using Delrin-AF for Slider 4/19
Delrin was purchased
Recommended Camping collapsible elastic poles 4/19
Ex. Collapsible Aluminum gun cleaning rod
No Twist Lock Mechanism restriction was lifted which expanded range of usable poles
Poles with Similar Collapsing Mechanism to the example Collapsible Aluminum gun cleaning rod as well as poles that expand/collapse with twist lock will be tested
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Production of Prototype is being rushed
Welding Aluminum will have to wait for another time
Resources or Information Required but not Available
N/A
Schedule
On field testing on 5/1
Prototype should be complete
Applicable Standards due on 4/28
Design Proposal Presentation on 5/3
Update Gantt chart.
Budget (list amount spent and amount remaining)
Amount spent: $298.43
Amount remaining: $701.57
Progress on Report and Webpage
Project Management Up to Week 4 Complete on Webpage by 4/26
Sections of Report Complete by 4/28
Background
Review of Existing Solutions
Statement of Requirements
Deliverables
Title page
Appendix with Individual Component Reports
Impact on Society
Applicable Standards