Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Frame
All parts manufactured, waiting on welding to finish, ETA sometime during the day on 6/4
Three legs with one foot on kayak and two legs forming bar to be on lap
Cameras
Team will be mounting this week
Swivel Hoist Ring
One hook on sampler, One hook on ball with string/cable connecting them together
Accomplishments from Previous Week
Finished machining all parts of the frame, Tom will be done with the welds by 6/5
Trigger to seal sample tube
Implement shackle release prototype (Joshua/Isabel)
Foot Hook
Replaced by trigger release (All)
Work on Report/Website (All)
Draft Poster due by 6/2 at midnight (All)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Camera Attachment onto pole/sampler (All)
Implement Camera mount
Ball Loss Prevention Feature (All)
Attach Swivel Hoist Ring to Ball
Add Hook to Sampler
Connect String/Cable to Swivel Hoist Ring and Hook on Sampler
Spacers for Frame
CAD-(Denny)
Machining-(Justin/Joshua)
Work on Final Report/Website Due 6/9 (All)
Draft Poster Final Draft 6/9 (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Frame: Three legs with lap bar feature (6/2)
Maybe add something on the bar to make it more comfortable to use?
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Height of the legs might be a concern if we are doing three leg set up with lap bar (5/31)
Might need to cut two of the legs shorter
3 legs: 1 long, 2 short
Ball (5/31)
Issues of loading spring
Gets lost easily
Possible Solution: Tap hole w/wire
Comments on Loading the Device (5/31)
Why is the foot swinging toward the operator?
Foot should have been loaded to the side?
Priorities (5/31)
Ball
Camera Mount
Trigger
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
N/A
Resources or Information Required but not Available
N/A
Schedule
Finish Final Design/Other Touches by 6/9
Foot Trigger Mechanism
Replace Foot Hook
Camera Attachment to Pole
Ball Lost Prevention Features
Final Draft of Report/Website due Friday, 6/9 at midnight
Final Draft of Poster due by Friday, 6/9 at midnight
Update Gantt chart.
Budget (list amount spent and amount remaining)
$490.75 spent, $509.25 remaining
Progress on Report and Webpage
Project Management up to Week 10 complete on webpage by 6/5
Implement Other Team's Comments and Feedback into Report and Website by 6/9
Everyone will be tidying up the Report and Website up until 6/9 at Midnight