11.0 SOFTWARE LIFE CYCLE DATA
Data is produced during the software life cycle to plan, direct, explain, define, record, or
provide evidence of activities. This data enables the software life cycle processes, system
or equipment certification, and post-certification modification of the software product. This
section discusses the characteristics, form, configuration management controls, and content
of the software life cycle data.
The characteristics of the software life cycle data are:
a. Unambiguous: Information is unambiguous if it is written in terms which only allow a
single interpretation, aided if necessary by a definition.
b. Complete: Information is complete when it includes necessary, relevant requirements
and/or descriptive material, responses are defined for the range of valid input data,
figures used are labeled, and terms and units of measure are defined.
c. Verifiable: Information is verifiable if it can be checked for correctness by a person
or tool.
d. Consistent: Information is consistent if there are no conflicts within it.
e. Modifiable: Information is modifiable if it is structured and has a style such that
changes can be made completely, consistently, and correctly while retaining the
structure.
f. Traceable: Information is traceable if the origin of its components can be
determined.
In addition, this guidance applies:
g. Form: The form should provide for the efficient retrieval and review of software fife
cycle data throughout the service life of the airborne system or equipment. The data
and the specific form of the data should be specified in the Plan for Software
Aspects of Certification.
Note:
(1) The software life cycle data may take a number of forms. For
example, it can be in written form, as computer files stored on
magnetic media, or as displays on a remote terminal. It may be
packaged as individual documents, combined into larger
documents, or distributed across several documents.
(2) The Plan for Software Aspects of Certification and the Software
Accomplishment Summary may be required as separate printed
documents by some certification authorities.
Software life cycle data can be placed in one of two categories associated with the
software configuration management controls applied: Control Category 1 (CC1) and
Control Category 2 (CC2) (subsection 7.3). This distinction provides a means to manage
development costs where less stringent controls can be applied without a reduction in
safety. The minimum control category assigned to each data item, and its variation by
software level is specified in Annex A.
The following data descriptions define the data generally produced to aid in the software
aspects of the certification process. The descriptions are not intended to describe all data
necessary to develop a software product, and are not intended to imply a particular data
packaging method or organization of the data within a package.
In addition to the data defined in these subsections, other data may be produced as
evidence to aid the certification process.
h. Control: If intended to be used for this purpose, this data should be defined in the
software plan which defines the process for which the data will be produced. While
the nature and content of this data may vary, as a minimum, CC2 controls should be
applied. Examples include memoranda and meeting minutes.
11.1 Plan for Software Aspects of Certification
The Plan for Software Aspects of Certification is the primary means used by the
certification authority for determining whether an applicant is proposing a software life cycle
that is commensurate with the rigor required for the level of software being developed. This
plan should include:
a. System overview: This section provides an overview of the system, including a
description of its functions and their allocation to the hardware and software, the
architecture, processor(s) used, hardware/software interfaces, and safety features.
b. Software overview: This section briefly describes the software functions with
emphasis on the proposed safety and partitioning concepts, for example, resource
sharing, redundancy, multiple-version dissimilar software, fault tolerance, and timing
and scheduling strategies.
c. Certification considerations. This section provides a summary of the certification
basis, including the means of compliance, as relating to the software aspects of
certification. This section also states the proposed software level(s) and summarizes
the justification provided by the system safety assessment process, including
potential software contributions to failure conditions.
d. Software life cycle: This section defines the software life cycle to be used and
includes a summary of each software life cycle and its processes for which detailed
information is defined in their respective software plans. The summary explains how
the objectives of each software life cycle process will be satisfied, and specifies the
organizations to be involved, the organizational responsibilities, and the system life
cycle processes and certification liaison process responsibilities.
e. Software life cycle data: This section specifies the software life cycle data that will
be produced and controlled by the software life cycle processes. This section also
describes the relationship of the data to each other or to other data defining the
system, the software life cycle data to be submitted to the certification authority, the
form of the data, and the means by which software life cycle data will be made
available to the certification authority.
f. Schedule: This section describes the means the applicant will use to provide the
certification authority with visibility of the activities of the software life cycle
processes so reviews can be planned.
g. Additional considerations.: This section describes specific features that may affect
the certification process, for example, alternative methods of compliance, tool
qualification, previously developed software, option-selectable software, usermodifiable
software, COTS software, field-loadable software, multiple-version
dissimilar software, and product service history.
11.2 Software Development Plan
The Software Development Plan includes the objectives, standards and software life
cycle(s) to be used in the software development processes. It may be included in the Plan
for Software Aspects of Certification. This plan should include:
a. Standards: Identification of the Software Requirements Standards, Software Design
Standards and Software Code Standards for the project. Also, references to the
standards for previously developed software, including COTS software, if those
standards are different.
b. Software life cycle: A description of the software life cycle processes to be used to
form the specific software life cycle(s) to be used on the project, including the
transition criteria for the software development processes. This description is
distinct from the summary provided in the Plan for Software Aspects of
Certification, in that it provides the detail necessary to ensure proper implementation
of the software life cycle processes.
c. Software development environment: A statement of the chosen software
development environment in terms of hardware and software, including:
(1) The chosen requirements development method(s) and tools to be used.
(2) The chosen design method(s) and tools to be used.
(3) The programming language(s), coding tools, compilers, linkage editors and loaders to be used.
(4) The hardware platforms for the tools to be used.
11.3 Software Verification Plan
The Software Verification Plan is a description of the verification procedures to satisfy the
software verification process objectives. These procedures may vary by software level as
defined in the tables of Annex A. This plan should include:
a. Organization: Organizational responsibilities within the software verification process
and interfaces with the other software life cycle processes.
b. Independence: A description of the methods for establishing verification
independence, when required.
c. Verification methods: A description of the verification methods to be used for each
activity of the software verification process.
(1) Review methods, including checklists or other aids.
(2) Analysis methods, including traceability and coverage analysis.
(3) Testing methods, including guidelines that establish the test case selection
process, the test procedures to be used, and the test data to be produced.
d Verification environment: A description of the equipment for testing, the testing and
analysis tools, and the guidelines for applying these tools and hardware test
equipment (see also paragraph 4.4.3, item b for guidance on indicating target
computer and simulator or emulator differences).
e. Transition criteria: The transition criteria for entering the software verification
process defined in this plan.
f. Partitioning considerations: If partitioning is used, the methods used to verify the
integrity of the partitioning.
g. Compiler assumptions: A description of the assumptions made by the applicant
about the correctness of the compiler, linkage editor or loader (paragraph 4.4.2).
h. Reverification Guidelines: For software modification, a description of the methods
for identifying the affected areas of the software and the changed parts of the
Executable Object Code. The reverification should ensure that previously reported
errors or classes of errors have been eliminated.
i. Previously developed software: For previously developed software, if the initial
compliance baseline for the verification process does not comply with this
document, a description of the methods to satisfy the objectives of this document.
j. Multiple-version dissimilar software: If multiple-version dissimilar software is used, a
description of the software verification process activities (paragraph 12.3.3).
11.4 Software Configuration Management Plan
The Software Configuration Management Plan establishes the methods to be used to
achieve the objectives of the software configuration management (SCM) process
throughout the software life cycle. This plan should include:
a. Environment: A description of the SCM environment to be used, including
procedures, tools, methods, standards, organizational responsibilities, and
interfaces.
b. Activities: A description of the SCM process activities in the software life cycle that
will satisfy the objectives for:
(1) Configuration identification: Items to be identified, when they will be
identified, the identification methods for software life cycle data (for example,
part numbering), and the relationship of software identification and airborne
system or equipment identification.
(2) Baselines and traceability: The means of establishing baselines, what
baselines will be established, when these baselines will be established, the
software library controls, and the configuration item and baseline traceability.
(3) Problem reporting: The content and identification of problem reports for the
software product and software life cycle processes, when they will be
written, the method of closing problem reports, and the relationship to the
change control activity.
(4) Change control: Configuration items and baselines to be controlled, when
they will be controlled, the problem/change control activities that control
them, pre-certification controls, post-certification controls, and the means of
preserving the integrity of baselines and configuration items.
(5) Change review: The method of handling feedback from and to the software
life cycle processes; the methods of assessing and prioritizing problems,
approving changes, and handling their resolution or change implementation;
and the relationship of these methods to the problem reporting and change
control activities.
(6) Configuration status accounting: The data to be recorded to enable reporting
configuration management status, definition of where that data will be kept,
how it will be retrieved for reporting, and when it will be available.
(7) Archive, retrieval, and release: The integrity controls, the release method and
authority, and data retention.
(8) Software load control: A description of the software load control safeguards
and records.
(9) Software life cycle environment controls: Controls for the tools used to
develop, build, verify and load the software, addressing items I through 7
above. This includes control of tools to be qualified.
(10) Software life cycle data controls: Controls associated with Control Category
1 and Control Category 2 data.
c. Transition criteria The transition criteria for entering the SCM process.
d. SCM data: A definition of the software life cycle data produced by the SCM
process, including SCM Records, the Software Configuration Index and the
Software Life Cycle Environment Configuration Index.
e. Supplier control: The means of applying SCM process requirements to sub-tier
suppliers.
11.5 Software Quality Assurance Plan
The Software Quality Assurance Plan establishes the methods to be used to achieve the
objectives of the software quality assurance (SQA) process. The SQA Plan may include
descriptions of process improvement, metrics, and progressive management methods. This
plan should include:
a. Environment: A description of the SQA environment, including scope, organizational
responsibilities and interfaces, standards, procedures, tools and methods.
b. Authority: A statement of the SQA authority, responsibility, and independence,
including the approval authority for software products.
c. Activities: The SQA activities that are to be performed for each software life cycle
process and throughout the software life cycle including:
(1) SQA methods, for example, reviews, audits, reporting, inspections, and
monitoring of the software life cycle processes.
(2) Activities related to the problem reporting, tracking and corrective action
system.
(3) A description of the software conformity review activity.
d. Transition criteria The transition criteria for entering the SQA process.
e. Timing: The timing of the SQA process activities in relation to the activities of the
software life cycle processes.
f. SQA Records: A definition of the records to be produced by the SQA process.
g. Supplier control: A description of the means of ensuring that sub-tier suppliers'
processes and outputs will comply with the SQA Plan.
11.6 Software Requirements Standards
The purpose of Software Requirements Standards is to define the methods, rules and tools
to be used to develop the high-level requirements. These standards should include:
a. The methods to be used for developing software requirements, such as structured
methods.
b. Notations to be used to express requirements, such as data flow diagrams and
formal specification languages.
c. Constraints on the use of the requirement development tools.
d. The method to be used to provide derived requirements to the system process.
11.7 Software Design Standards
The purpose of Software Design Standards is to define the methods, rules and tools to be
used to develop the software architecture and low-level requirements. These standards
should include:
a. Design description method(s) to be used.
b. Naming conventions to be used.
c. Conditions imposed on permitted design methods, for example, scheduling, and the
use of interrupts and event-driven architectures, dynamic tasking, re-entry, global
data, and exception handling, and rationale for their use.
d. Constraints on the use of the design tools.
e. Constraints on design, for example, exclusion of recursion, dynamic objects, data
aliases, and compacted expressions.
f. Complexity restrictions, for example, maximum level of nested calls or conditional
structures, use of unconditional branches, and number of entry/exit points of code
components.
11.8 Software Code Standards
The purpose of the Software Code Standards is to define the programming languages,
methods, rules and tools to be used to code the software. These standards should include:
a. Programming language(s) to be used and/or defined subset(s). For a programming
language, reference the data that unambiguously defines the syntax, the control
behavior, the data behavior and side-effects of the language. This may require
limiting the use of some features of a language.
b. Source Code presentation standards, for example, line length restriction,
indentation, and blank line usage and Source Code documentation standards, for
example, name of author, revision history, inputs and outputs, and affected global
data.
c. Naming conventions for components, subprograms, variables, and constants.
d. Conditions and constraints imposed on permitted coding conventions, such as the
degree of coupling between software components and the complexity of logical or
numerical expressions and rationale for their use.
e. Constraints on the use of the coding tools.
11.9 Software Requirements Data
Software Requirements Data is a definition of the high-level requirements including the
derived requirements. This data should include:
a. Description of the allocation of system requirements to software, with attention to
safety related requirements and potential failure conditions.
b. Functional and operational requirements under each mode of operation.
c. Performance criteria, for example, precision and accuracy.
d. Timing requirements and constraints.
e. Memory size constraints.
f. Hardware and software interfaces, for example, protocols, formats, frequency of
inputs and frequency of outputs.
g. Failure detection and safety monitoring requirements.
h. Partitioning requirements allocated to software, how the partitioned software
components interact with each other, and the software level(s) of each partition.
11.10 Design Description
The Design Description is a definition of the software architecture and the low-level
requirements that will satisfy the software high-level requirements. This data should include:
a. A detailed description of how the software satisfies the specified software high-level
requirements, including algorithms, data structures, and how software requirements
are allocated to processors and tasks.
b. The description of the software architecture defining the software structure to
implement the requirements.
c. The input/output description, for example, a data dictionary, both internally and
externally throughout the software architecture.
d. The data flow and control flow of the design.
e. Resource limitations, the strategy for managing each resource and its limitations, the
margins, and the method for measuring those margins, for example, timing and
memory.
f. Scheduling procedures and inter-processor/inter-task communication mechanisms,
including time-rigid sequencing, preemptive scheduling, Ada rendezvous, and
interrupts.
g. Design methods and details for their implementation, for example, software data
loading, user-modifiable software, or multiple-version dissimilar software.
h. Partitioning methods and means of preventing partition breaches.
i. Descriptions of the software components, whether they are new or previously
developed, and, if previously developed, reference to the baseline from which they
were taken.
j. Derived requirements resulting from the software design process.
k. If the system contains deactivated code, a description of the means to ensure that
the code cannot be enabled in the target computer.
l. Rationale for those design decisions that are traceable to safety-related system
requirements.
11.11 Source Code
This data consists of code written in source language(s) and the compiler instructions for
generating the object code from the Source Code, and linking and loading data. This data
should include the software identification, including the name and date of revision and/or
version, as applicable.
11.12 Executable Object Code
The Executable Object Code consists of a form of Source Code that is directly usable by
the central processing unit of the target computer and is, therefore, the software that is
loaded into the hardware or system.
11.13 Software Verification Cases and Procedures
Software Verification Cases and Procedures detail how the software verification process
activities are implemented. This data should include descriptions of the:
a. Review and analysis procedures: Details, supplementary to the description in the
Software Verification Plan, which describes the scope and depth of the review or
analysis methods to be used.
b. Test cases: The purpose of each test case, set of inputs, conditions, expected results
to achieve the required coverage criteria, and the pass/fail criteria.
c. Test procedure: The step-by-step instructions for how each test case is to be set up
and executed, how the test results are evaluated, and the test environment to be
used.
11.14 Software Verification Results
The Software Verification Results are produced by the software verification process
activities. Software Verification Results should:
a. For each review, analysis and test, indicate each procedure that passed or failed
during the activities and the final pass/fail results.
b. Identify the configuration item or software version reviewed, analyzed or tested.
c. Include the results of tests, reviews and analyses, including coverage analyses and
traceability analyses.
11.15 Software Life Cycle Environment Configuration Index
The Software Life Cycle Environment Configuration Index (SECI) identifies the
configuration of the software life cycle environment. This index is written to aid
reproduction of the hardware and software life cycle environment, for software
regeneration, reverification, or software modification, and should:
a. Identify the software life cycle environment hardware and its operating system
software.
b. Identify the software development tools, such as compilers, linkage editors and
loaders, and data integrity tools (such as tools that calculate and embed checksums
or cyclical redundancy checks).
c. Identify the test environment used to verify the software product, for example, the
software verification tools.
d. Identify qualified tools and their associated tool qualification data.
Note: This data may be included in the Software Configuration Index.
11.16 Software Configuration Index
The Software Configuration Index (SCI) identifies the configuration of the software
product.
Note: The SCI can contain one data item or a set (hierarchy) of data items. The SCI
can contain the items listed below or it may reference another SCI or other
configuration identified data that specifies the individual items and their
versions.
The SCI should identify:
a. The software product.
b. Executable Object Code.
c. Each Source Code component.
d. Previously developed software in the software product, if used.
e. Software life cycle data.
f. Archive and release media.
g. Instructions for building the Executable Object Code, including, for example,
instructions and data for compiling and linking; and the procedures used to recover
the software for regeneration, testing or modification.
h. Reference to the Software Life Cycle Environment Configuration Index (subsection
11. 15), if is packaged separately.
i. Data integrity checks for the Executable Object Code, if used.
Note: The SCI may be produced for one software product version or it may be
extended to contain data for several alternative or successive software
product versions.
11.17 Problem Reports
Problem reports are a means to identify and record the resolution to software product
anomalous behavior, process non-compliance with software plans and standards, and
deficiencies in software life cycle data. Problem reports should include:
a. Identification of the configuration item and/or the software life cycle process activity
in which the problem was observed.
b. Identification of the configuration item(s) to be modified or a description of the
process to be changed.
c. A problem description that enables the problem to be understood and resolved.
d. A description of the corrective action taken to resolve the reported problem.
11.18 Software Configuration Management Records
The results of the SCM process activities are recorded in SCM Records. Examples
include configuration identification lists, baseline or software library records, change history
reports, archive records, and release records. These examples do not imply records of
these specific types need to be produced.
Note: Due to the integral nature of the SCM process, its outputs will often be
included as parts of other software life cycle data.
11.19 Software Quality Assurance Records
The results of the SQA process activities are recorded in SQA Records. These may
include SQA review or audit reports, meeting minutes, records of authorized process
deviations, or software conformity review records.
11.20 Software Accomplishment Summary
The Software Accomplishment Summary is the primary data item for showing compliance
with the Plan for Software Aspects of Certification. This summary should include:
a. System overview: This section provides an overview of the system, including a
description of its functions and their allocation to hardware and software, the
architecture, the processor(s) used, the hardware/software interfaces, and safety
features. This section also describes any differences from the system overview in
the Plan for Software Aspects of Certification.
b. Software overview: This section briefly describes the software functions with
emphasis on the safety and partitioning concepts used, and explains differences from
the software overview proposed in the Plan for Software Aspects of Certification.
c. Certification considerations: This section restates the certification considerations
described in the Plan for Software Aspects of Certification and describes any
differences.
d. Software characteristics: This section states the Executable Object Code size, timing
and memory margins, resource limitations, and the means of measuring each
characteristic.
e. Software life cycle : This section summarizes the actual software life cycle(s) and
explains differences from the software life cycle and software life cycle processes
proposed in the Plan for Software Aspects of Certification.
f. Software life cycle data: This section references the software life cycle data
produced by the software development processes and integral processes. It
describes the relationship of the data to each other and to other data defining the
system, and the means by which software life cycle data will be made available to
the certification authority. This section also describes any differences from the Plan
for Software Aspects of Certification.
g. Additional considerations: This section summarizes certification issues that may
warrant the attention of the certification authority and references data items
applicable to these issues, such as issue papers or special conditions.
h. Software identification: This section identifies the software configuration by part
number and version.
i. Change history: If applicable, this section includes a summary of software changes
with attention to changes made due to failures affecting safety, and identifies changes
from the software life cycle processes since the previous certification.
j. Software status: This section contains a summary of problem reports unresolved at
the time of certification, including a statement of functional limitations.
k. Compliance statement: This section includes a statement of compliance with this
document and a summary July 2, 1996 of the methods used to demonstrate
compliance with criteria specified in the software plans. This section also addresses
additional rulings and deviations from the software plans, standards and this