The subsequent is an optimum site plan and phasing construction scheme for the Mollstrasse/Otto-Braun-Strasse development, aligned with RIBA Stage 5 (Technical Design) and German BaustellV/DGUV regulations. The scheme maximizes efficiency by zoning storage, access routes, welfare facilities, and crane operations, and addresses CDM 2015 safety requirements. A logistics plan minimizes congestion, and security measures (hoarding, CCTV, fire points) ensure a safe worksite.
Phasing has a formal five-stage process, with the potential for concurrent work flows, early handovers, and risk minimization. Enabling works, substructure, superstructure, fit-out, and Soft Landings handover are some of the key phases, a system which ensures smooth transition to occupancy by user engagement, performance monitoring, and post-occupancy review.
Justified by safety, efficiency, and regulation, this proposal finds a balance of multidisciplinary coordination (QS + CPM) and RICS/CIOB standards to present a feasible, client-usable proposal. The utilization of visual aids ( 3D diagrams) and HSE-compliant temporary works policies gives it further strength.
Overview: The site layout must facilitate safe, efficient movement of labour, plant, materials, and waste. comply with CDM 2015 regulations.
Storage Zones
Clearly marked areas for materials and equipment, separated and shown in site Layout.
Access Routes
Routes for vehicles, separate pedestrian walkways shown in Site Layout.
Welfare Facilities
Toilets, break areas, and first-aid stations placed near the site entrance shown in Site Layout.
Site Offices
Clear visibility of operations without obstructing vehicle routes shown in Site Layout .
Cranes/Heavy Plant
Strategically positioned to cover maximum area with minimal repositioning in Site Layout
· Logistics Plan will be followed for deliveries to reduce storage needs and congestion.
· Security & Safety: Temporary fencing ( Hoarding sheets ) , CCTV, fire points ( evacuation points ), and emergency exits clearly demarcated in Site Layout.
A good layout optimizes site efficiency, reduces double handling of materials, improves safety, and minimize downtime. It also reduces environmental impact through better logistics.
Figure 1: Site Layout showing and its temporary site arrangements for execution.
Figure 2: Site Welfare facilities for staffs and workers, pedestrian crossing, scaffolding line, Entry and Exit way
Overview: Site Phasing breaks down construction process into manageable sections or zones, This enabling smoother coordination and potential early handovers.
Figure 3: Site Boundary Hoarding Sheets
Phase 1 – Enabling Works & Site Setup:
Site hoarding, temporary utilities, welfare setup.
Phase 2 – Substructure & Groundwork's:
Excavation will be Split into quadrants to allow parallel excavation and foundation work.
Coordination with underground utility installation will be followed for smooth process.
Figure 4: Piles Laying details
Figure 5: Surface preparation for Raft Foundation
Phase 3 – Superstructure & Envelope:
Zone-based construction method will be followed (e.g., East Wing then West Wing).
Early closure of building envelope to enable internal works.
Figure 6: East Wing Layout
Figure 7: West Wing Layout
Phase 4 – Internal Fit-Out & Services:
Wing by wing to enable staged commissioning
Phase 5 – Final Testing, Commissioning & Handover:
Follow the Soft Landings methodology for smooth transition
The Soft Landings process is a framework developed to ensure a smoother transition from construction to occupation of a building, with a focus on improving building performance, user satisfaction, and lifecycle value. It is closely aligned with the UK Government’s policy on achieving better outcomes for public building investments and is incorporated into the Government Soft Landings (GSL) initiative.
The process typically follows these five key stages:
1. Inception and Briefing
Objective: Align project goals with client and end-user needs from the outset.
Appoint a Soft Landings Champion (usually from the design team or client).
Define clear performance objectives (energy use, comfort, FM needs).
Engage end-users and facilities management (FM) early.
Integrate Soft Landings into project brief and procurement strategy.
Deliverables:
GSL performance targets.
Stakeholder engagement plan.
Project Soft Landings strategy.
2. Design and Construction
Objective: Ensure design aligns with performance and usability goals.
Hold regular design reviews and value engineering sessions.
Model predicted performance (e.g., using BIM or energy modeling).
Incorporate feedback from FM and users into design choices.
Maintain a focus on it's build ability, commissioning, and operational needs.
Deliverables:
Updated performance tracker.
Design-for-performance documentation.
Commissioning and handover strategy.
3. Pre-handover (Commissioning and Preparation)
Objective: Prepare the building, users, and management team for occupancy.
Conduct full system testing and commissioning (e.g., HVAC, lighting).
Provide user training sessions and building manuals.
Carry out technical reviews to ensure design intent is met.
Simulate building usage scenarios and rectify issues.
Deliverables:
Handover documentation and user guides.
Commissioning records.
Operational readiness checklist.
4. Handover and Initial Aftercare
Objective: Provide support during the crucial first few weeks of occupancy.
Keep the design/construction team involved post-handover.
Monitor systems, respond to user concerns, and fix early issues.
Conduct on-site presence (typically for 4-6 weeks).
Adjust controls and settings for optimal comfort and efficiency.
Deliverables:
Aftercare reports.
Fine-tuned building systems.
Post-occupancy issue log.
5. Post-occupancy Evaluation (POE) and Long-term Aftercare
Objective: Assess building performance and make long-term improvements.
Conduct POE at 3, 6, and 12 months post-occupation.
Evaluate energy use, indoor environment, and user satisfaction.
Compare actual vs predicted performance.
Inform future projects through lessons learned.
Deliverables:
POE reports.
Lessons learned summary.
Feedback loop to design and FM teams.
RIBA Stage Soft Landings Activity
Stage 0–1: Define performance outcomes, appoint champion
Stage 2–3: Design review, engage FM, embed Soft Landings into spec
Stage 4: Commissioning plan, user training prep
Stage 5: Pre-handover tests, occupant training
Stage 6: Aftercare, fine-tuning, POE
Stage 7: Ongoing monitoring and lessons learned
Benefits of Soft Landings
· Improved building performance and energy efficiency.
· Reduced post-occupancy complaints.
· Higher user satisfaction and comfort.
· Better-informed design and FM teams.
· Optimized lifecycle cost and asset management.
Phased delivery supports resource management, reduces rework, and enables staggered commissioning, improving client satisfaction. It also helps in managing risks by limiting disruptions to ongoing phases.
HSE Policy for Site Temporary Works in Germany
1. Policy Statement
2. Scope
3. Legal and Regulatory Framework
This policy outlines the principles and procedures to ensure the safe planning, design, installation, use, and dismantling of all temporary works on construction sites in Germany. Temporary works include scaffolding, shoring, form work, hoardings, access platforms, and site accommodations.
The company commits to:
Complying with the BaustellV, DGUV regulations, and DIN EN standards.
Eliminating or minimizing health and safety risks.
Promoting a culture of safe practices through training, communication, and continuous monitoring.
This policy applies to all employees, subcontractors, suppliers, and consultants involved in:
Design and supervision of temporary works.
On-site erection and dismantling of structures.
Inspections and maintenance during use.
Baustellenverordnung (BaustellV) – Construction Site Ordinance, ensuring coordination and safety planning.
DGUV Vorschrift 38 – Health and Safety regulations for construction work.
TRBS 1201 & TRBS 1111 – Technical rules for operational safety and risk assessment.
DIN EN 12811 – Requirements for scaffolding.
Arbeitsstättenverordnung (ArbStättV) – Workplace ordinance for site welfare and facilities.
4. Risk Assessment and Planning
5. Design and Supervision
6. Control Measures
Temporary works must be included in the SiGe-Plan (Health & Safety Plan) developed by the SiGeKo (Health and Safety Coordinator).
A specific risk assessment must be conducted before the start of any temporary works.
Design must be approved and signed off by a qualified engineer or Temporary Works Coordinator (TWC).
Load calculations and stability must comply with DIN EN standards.
Only trained professionals may design or approve temporary structures.
The Temporary Works Register must be maintained.
Method statements must be created for installation and dismantling.
Supervision and inspection shall be continuous throughout the works.
Scaffolding must be inspected by a qualified person after erection, modifications, extreme weather, and at least every 7 days.
Signage, barriers, and load limitations must be clearly marked.
Emergency plans and evacuation routes must consider temporary structures.
Proper access/egress, fall protection, and weather protection must be provided.
7. Training and Competency
8. Inspection and Monitoring
9. Incident Reporting
All workers involved in temporary works must receive:
Safety induction specific to temporary works.
Toolbox talks.
Training per DGUV and BaustellV requirements.
Site supervisors and TWCs must hold verifiable certifications.
Regular inspections must be documented and reviewed.
Any defective structure must be immediately rectified or taken out of service.
Audits by the HSE Manager and TWC are mandatory at key milestones.
Any incidents, near misses, or structural issues involving temporary works must be reported immediately.
Incident investigations must be documented and shared with the HSE team and relevant authorities.
10. Environmental Considerations
11. Review and Continuous Improvement
Waste from temporary works (e.g., formwork timber, scaffold boards) must be managed per the Kreislaufwirtschaftsgesetz (Circular Economy Act).
Noise, dust, and vibration must be minimized during installation and removal.
This policy is reviewed annually or after any major incident or regulatory update.
Lessons learned are incorporated into future planning and training.