Project Schedule
Learning > Record Pages > Project Schedule
NOTICE: Starting 5/16, add "@dot.state.co.us" to the end of your username when logging in to PMWeb.
The Project Schedule record provides a single source for Project Managers to manage project milestones. Users can use dates from the schedule in other records (e.g., deliverables, project changes) or to drive the duration of the construction contract expenditure forecast.
Access: This record is located in the Schedules module of PMWeb.
Related Pages: Deliverables (Stage Gates); Master Project Record; Project Changes; Forecasts; Program: Schedule Milestone Look Ahead Report
The following job aids and reference guides are relevant to the Schedules record:
To request additional training or documentation, please submit a Help Request in PMWeb.
To reduce errors, ensure date columns are consistent with Start/Finish or Finish/Start for Planned, Actual, and Baseline
Actual Start/Finish columns must be visible for the "Status Schedule" WalkMe step-by-step guidance to function properly
Filtering by total float "0" will provide all critical activities
It is recommended to baseline schedules immediately after configuring the schedule template. This ensures cascaded changes and makes sure that the progress of each of the scheduled tasks are easily identifiable
Baselines are required at FIR
Approval to change the baseline schedule should adhere to regional policies and processes
Progressing tasks could include the need to break out tasks into different activities or change dependencies to accurately show schedule progression
Add dates to the Actual Start and Actual Finish columns only when an activity has started or finished. For planned dates, use the Start and Finish columns.
Status dates should be updated as the final step when progressing the schedule, but the PM should take time after updating the status date to identify and/or resolve any resulting issues
Once the project starts, monthly updates are recommended
Milestones do not have a duration
Task durations cannot be edited for parent (summary) tasks
You can change the relationship between tasks (parent/child) by either:
Selecting a task and clicking on the "Outdent" and "Indent" buttons in the schedule toolbar (shown below).
OR
Dragging and dropping a task and nesting it directly under an appropriate predecessor task. A task is properly nested when the green arrow appears where you place the task (shown below). If your task nests incorrectly (for example, within its predecessor instead of directly under), then select and drag the task line again to fix it.
Incorrect dependencies appear in the Gantt chart as red relationships between activities. Correct dependencies will show up as blue.
Dependencies can be created in the Gantt chart by selecting the beginning or end of the first task, holding the right mouse button and dragging it to the beginning or end of the second task. All types of dependencies can be created this way.
Lags should be minimized. It is recommended that long lead times be included in the schedule as tasks and labeled appropriately for increased visibility and understanding of impacts to the schedule.
Task Codes - Numerical identifier for tasks within a project schedule. Task codes allow users to customize the order and manage tasks in the schedule.
Milestone - Milestone tags assigned to the appropriate milestones ensure that the dates are pulled into all of the project/schedule reports and related records that list milestone dates.
Forecasting - Assign to the parent (summary) task of the work to be completed if multiple activities are in the schedule (Design, ROW, Utilities...). Ensure the construction task is assigned has the forecast tag "Construction".
Your Project Schedule manages important project dates and timelines and connects these to your deliverables (Stage Gates) in the system.
Your Project Schedule includes:
Record Menu - Here, you can select any project Schedule, save your schedule, add a new schedule, delete the current schedule, share your schedule, and use the Schedule Setup button for Guided Help.
Schedule Tabs - Schedule tabs provide a place for notes, attachments, and notifications for your project schedule.
Project Data - Clicking the Expand icon here opens a panel with your specific project data to review. Use this menu to confirm your Project Status date.
Project Schedule - Edit your project start date and fine-tune your project task duration for any task. All items on your schedule are related and auto-adjust to any date changes made in this area.
Task Details - Here, you can document task details, including Dependencies and Project Codes.
The schedule views can be modified, but only for the duration of time that you are logged in. The views reset every night, so it is recommended to complete a schedule configuration, modification, or status update within a single session to reduce re-work.
Task columns can be added or removed with the "Column list" button.
The amount of information displayed within each of the 3 main columns can be modified by dragging the blue bars.
Toggling the filter on or off will add a task bar at the top that will provide text, number and date filter opportunities.
With your Project Schedule open, you can adjust your Start date and the duration of any tasks listed within your schedule.
Update Start Date - To update your Schedule start date, type or select a new date by clicking the calendar icon to replace the current start date.
Update Duration - In the Duration field for any task, click to replace the existing duration time with the new duration then press Enter to update this and all related Schedule dates based on your new duration.
Schedule Save - Click this Save icon any time you are making changes in the Schedule area displayed here. This ensures your schedule changes are saved.
Keeping the Status date accurate is an important step in maintaining an accurate project schedule.
Steps:
Click the Expand icon to view your project information in the Schedule record.
2. Updating the Status date should be the final step in updating the schedule. This is the date that the schedule tasks have been progressed to. Any unstarted task will be "moved out" recognizing that the schedule is current to the date you updated the schedule on.
3. Click the Condense icon to close your Schedule Detail view.
4. Click Save to save your Changes.
Click the + icon in your Schedule header to add a new Task row.
Enter a Code and Task Name for your task in the newly provided columns.
The new Code must fall between your currently existing task codes in the Schedule, depending on your preferred area of placement.
Ex. set a code of 040 if you'd like the new task between code 030 and 050
Click the Save icon to save your new task.
4. With your mouse, click and drag the newly created Task to the corresponding area of your Schedule, based on the Code column.
5. As needed, use the indention icons to align your task correctly in the Schedule view.
6. Click the blue hyperlink in your new task row to populate its information in the Details section below your Schedule.
7. Click Dependencies to relate this new task to a Predecessor and Successor task in the Schedule.
8. Click Add to add a predecessor for this new task. This connects the tasks and due dates in the Schedule.
9. Select your Predecessor task from the drop-down list provided and click Save within the table.
10. Repeat Steps 8 & 9 for your Successor task.
*Click Save within each table to save your updates.
Click the check mark from the top menu bar once you are ready to baseline your schedule at FIR, have received Program Engineer approval to re-baseline, or would like to baseline (unofficial) before FIR in order to track task dates.
The tool will populate every tasks planned start/finish date to the baseline start/finish dates.
The Project schedule can be shared in multiple ways depending on the audience's needs. The first method can be copying and emailing the link although this method is outside of PMWeb but can be lost in the email Inbox.
The more preferable distribution method is utilizing the "Notification" functionality within PMWeb. The benefit is this keeps a log of when and to whom the schedule has been sent to. The only drawback is the intended audience must have access to PMWeb.
Critical Path Method (CPM) Scheduling - CPM Scheduling is a logic-based planning technique using activity durations and relationships between activities to calculate a schedule determining the minimum total project duration and the interdependencies of all activities.
Critical Path - The longest logical path through the CPM network driven by calendars, constraints, and activity logic. It consists of activities that determine the shortest time for project completion and the sequence of activities such that a delay to any of the activities on the critical path will prolong contractual project milestones, such as project completion.
Critical Activity — An activity that must be completed on schedule for the project to finish on time. If a critical activity is delayed, the project finish date might also be delayed.
Status Date (Data Date) – The starting point from which to schedule all remaining work. It can also be considered the cut-off date wherein all work before this date has actual starts, actual finishes, or both.
Dependencies (Relationships) – Logical ties between scheduled tasks to create an order to activities.
Duration – The length of time a task requires
Constraint – The overriding of logic with a set date.
Lag – Added duration to a relationship.
Float ― The amount of delay activity can experience before it impacts the completion of the schedule.
Total Float – The amount of time between the earliest date an activity can start and the latest date when an activity must start, or the earliest date an activity can finish and the latest date when an activity can finish before the activity causes a delay to the project.
Free Float – The amount of time an activity can be delayed without delaying the Early Start or Early Finish of its successor activity or activities.
Slack ― Microsoft Project uses the term slack in place of float.
Gantt Chart – A time-scaled graphical display of the project’s schedule.
Milestone – A scheduled task without a duration.
Parent Task (Summary Task) – A schedule task without any relationships (dependencies) that provides a summary of the child tasks.
The Schedule record impacts any reports that use milestones or schedule task dates.
There is no workflow associated with this record.
The Schedule record integrates with or triggers to/from the following:
Schedule record Milestones are used in many records throughout PMWeb, any necessary changes to Milestone dates should be made within the Schedule record.
Schedule record Milestones are sent to OnBase.
Schedule record task can be linked to deliverables in the Stage Gates record.
The Forecast tag in the Schedule record identifies the construction period used to drive Forecast and Estimate Capture records.
Do I update the Schedule Status Date monthly, or at major milestones?
This depends on your region. Most regions recommend updating your Schedule record at least monthly, but more often if needed to record major milestones.
Why did the update for my project’s “AD (milestone)” date on the PMWeb Schedule not change?
Perhaps the change didn’t get saved. Follow the steps outlined below to ensure your schedule updates are saved
Why is my project’s PMWeb “AD (milestone)” date not reflected on the Go Sheet?
The “Scheduled Ad Date” on the SAP cj20n Business Manager (BM) tab is the source for the “AD Date” on the Go Sheet.
When I update the PMWeb “AD (milestone)” date, what’s the process to update the SAP AD date?
Follow your Region’s process for updating the SAP AD date. In R2, project staff need to request an Ad date change via email to the Business Office: To: Mary Balchuck; Cc: Jason Ahrens; Michael Nusen. The Business Office will change the SAP cj20n BM tab “Scheduled AD Date”.
Where is the Go Sheet (Anticipated Projects Advertisements Next 180 Days) located?
Navigate to the Current & Future Bidding Opportunities page. Once on the web page, click "GoSheet Anticipated Project Report" link.
Do we need to update the “AD Certainty” field (green/yellow/red) on the SAP cj20n, Project Manager Tab?
No. The “AD Certainty” field does not need to be managed because the field was removed from the Go Sheet (as per the decision made at the 6-8-22 PRTO TAC meeting).
Where is the bi-weekly calendar for project Ad dates?
Visit the Bid Advertisement Calendar page link here. Once on the webpage, click the "Bid Advertisement Schedule" link, as shown below, to download the calendar.
How do I create a Construction-Phase-Only Schedule for Non-Capital Engineering Projects?
Here’s the 8-click method to Delete pre-con Schedule tasks as shown below:
Click the "Select or unselect all rows" white square.
Deselect the 6 Construction Phase/Tasks.
Click the "X" Delete Selected Rows button.
Click the “small” & “big” Save buttons to save changes
Are there any reports available for the schedule record?
There are multiple reports available for the schedule record including: 180 Day Lookahead, Program View, Schedule Lookahead, Scheduling Gantt Chart, Projects Over/Under Schedule, Scheduling Dashboard.
Can I create reminders to update the schedule?
Yes. To do so, right-click on any task or milestone line in the schedule to open the "Define Reminder" window. In the resultant window, enter a reminder date, select users/contacts to remind, and the method of communication. Click the "Save and Exit" icon when finished.
Where can I find more information on schedules?
For more information on the Schedule record in PMWeb, refer to the training materials located in the "Schedules" folder in the Tips and Tricks Library.