SAP MRP3 View

MRP 3 View: 

The following are the fields in MRP 3 View: 

Strategy Group:

A Strategy Group represents the procedure used for planning a material. Primarily for Made to Stock the strategy is “10” in SAP and for Made to Order the Strategy is “20” in SAP.

 

There are many other strategies in the system other than Made-to-order and Made-to-Stock like

 

Planning with final assembly - Strategy Group or Strategy = 40 

 

This is a made-to-stock scenario where production is not only driven by planned independent requirements set in MD61 for a material, but any shortage in stock which are recognized by the incoming sales orders are also covered by MRP. Therefore the system plans for the quantities entered in planned independent requirement as well as plans for any shortages that may arise because of incoming demand.

 

In a mere Made-to-stock scenario (Strategy = 10) , the production is only driven by planned independent requirements set in MD61 for a material and any shortage identified by incoming demand does not result in additional procurement proposals created in MRP to cover that shortage.

 

You can use Strategy - 10, when you know that the forecasted demand is correct and you cannot afford to produce more than that.

 

You can use Strategy - 40 when you want to accomodate for evergrowing changes in demand and satisfy the shortages not identified by the forecast.

 

Note - Using Strategy 40 is wise. 

 

Make-to-Order - Strategy Group or Strategy = 20 

 

In a make-to-order scenario, the production is initiated upon receipt of an incoming customer requirement, i.e., production is made specifically for the customer requirements.

 

In this case the production order and the stock is assigned to the customer order avioding any divertions to another customer demand for a similar or same product. 

Consumption Modes

The consumption mode controls the direction on the time axis in which the system consumes requirements.

Backward Consumption period: 

Determines how far in the past on the time axis, the system should look for consuming the PIRS (planned independent requirement). The Sales Orders, Dependent Requirements, etc are assigned to & consume the PIR quantities that within this consumption period (before the requirements date

Forward Consumption period

Determines how far in the future on the time axis, the system should look for consuming planned independent requirement. The Sales orders, Dependent Requirements, etc are assigned to & consume the PIR quantities that within this consumption period (after the requirements date).

Availability Check

Using this field the system specifies whether and how the system checks availability and generates requirements for materials planning. It specifies which MRP elements the System takes into account (Purchase Orders, Production/Process Orders, etc) during availability check.

 

 

All the site contents are Copyright © www.sapsword.com and the content authors. All rights reserved.

All product names are trademarks of their respective companies.  The site www.sapsword.com is in no way affiliated with SAP AG. Every effort is made to ensure the content integrity. 

Information used on this site is at your own risk.

 The content on this site may not be reproduced or redistributed without the express written permission of

www.sapsword.com or the content authors. 

 

Sitemap                                                                                                                                                                                                                                                                                                                                                       Sitemap