Here are some important formulas which you should understand and remember for PMP exam perspective.
1. Present Value=(Future Value)/(1+r)^n
Where r is rate of return.
n is number of time period.
2. Expected Activity Duration(3 point estimate)
triangular distribution- (P+M+O)/3
beta distribution=(P+4M+O)/6
Where P=Pessimistic Estimate
M=Most likely Estimate
O=Optimistic estimate
3. Standard deviation =(P-O)/6
4 Activity Variance =((P-O)/6)^2
5. Range of estimate =Expected Activity Duration(+ - )Standard deviation
6. Point of total Assumption= (ceiling Price-Target Price)/Buyer's Share ratio + target cost
7. Cost Variance (CV)= Earned Value(EV)-Actual cost(AC)
8. Schedule Variance(SV)=Earned Value(EV)- Planed Value(PV)
9. Variance at Completion(VAC)=Budget At Completion(BAC)-Estimate At completion(EAC)
10. Cost Performance Index(CPI)=EV/AC
11.Schedule Performance Index(SPI)=EV/PV
12. Estimate at Completion(EAC)=
i)BAC/CPI - Current Performance will continue.
ii)AC+(BAC-EV)- Future work will be at per plan
iii)AC+Bottom up ETC- Re planning remaining work
iv)AC+(BAC-EV)/(CPI*SPI)- Taking cost and schedule on remaining work.
13. Estimate To Complete(ETC)=
i)Estimate at completion(EAC)- Actual Cost(AC)
ii)Re estimate
14. To complete performance Index(TCPI)=
i)Remaining work/Remaining Cost=(BAC-EV)/(BAC-AC)
ii)Remaining work/New Estimated Remaining cost=(BAC-EV)/(EAC-AC)
15. Expected Monetary Value (EMV)=Probability(P)* Impact(I)
16. Total Float =
i)Late Start(LS)- Early Start(ES)
ii)Late Finish(LF)-Early Finish(EF)
17.Communication Channel =n*(n-1)/2.
Where n is number of stakeholders.